HB1342: HB1342 Highways; procedures and remedies when a highway improvement project is delayed due to removal, relocation, or adjustment of utility facilities; provide
2025-2026 Regular Session · Introduced version · Last action February 18, 2026
26 LC 39 4884
House Bill 1342
By: Representatives McDonald III of the 26 th, Jasperse of the 11 th, Hawkins of the 27 th,
Parsons of the 44th, Cox of the 28th, and others
A BILL TO BE ENTITLED
AN ACT
To amend Part 1 of Article 6 of Chapter 6 of Title 32 of the Of ficial Code of Georgia1
Annotated, relating to regulation of maintenance and use of pub lic road relative to public2
utilities in general, so as to provide for procedures and remed i e s w h e n a h i g h w a y3
improvement project is delayed due to the removal, relocation, or adjustment of utility4
facilities; to provide for damages; to repeal provisions relati ve to mediation boards; to5
provide for related matters; to repeal conflicting laws; and for other purposes.6
BE IT ENACTED BY THE GENERAL ASSEMBLY OF GEORGIA:7
SECTION 1.8
Part 1 of Article 6 of Chapter 6 of Title 32 of the Official Co de of Georgia Annotated,9
relating to regulation of maintenance and use of public road re lative to public utilities in10
general, is amended by revising Code Section 32-6-171, relating to authority of department11
to order removal, relocation, or adjustment of utility facilities, as follows:12
"32-6-171.13
(a) Any utility using, occupying, or adjacent to any part of a public road which the14
department has undertaken to improve or intends to improve shal l remove, relocate, or15
make the necessary adjustments to its facility when, in the rea sonable opinion of the16
H. B. 1342
- 1 -
26 LC 39 4884
department, the facility constitutes an obstruction or interfer e n c e w i t h t h e u s e o r s a f e17
operation of such road by the traveling public or when, in the reasonable opinion of the18
department, the facility will interfere with such contemplated construction or maintenance. 19
In undertaking such removal, relocation, or adjustment, if the department has notified the20
utility in writing that the facility constitutes an obstruction or interference with the21
construction, use, or safe operation of the roadway, then the utility shall be exempt from22
the requirements of Code Sections 22-1-10 and 22-1-10.1. Nothing in this Code section23
shall be construed so as to deprive any utility relocated from a location in which it owned24
a property interest of compensation for such interest.25
(b) Whenever the department reasonably determines it necessary to have a utility facility26
removed, relocated, or adjusted, the department shall give to t he utility at least 60 days'27
written notice directing it to begin the physical removal, or r elocation, or adjustment of28
such utility obstruction or interference. If such notice is part of a highway improvement29
project, it is normally shall be provided at the date of advertisement or award; provided,30
however, that. However, prior to the notice directing the physical removal, relocation, or31
adjustment of a utility facility, the utility and the departmen t shall adhere to the32
department's utility relocation procedures for public road impr ovements which shall33
include but not be limited to the following:34
(1) The department's submission by the department to the utility of a letter and set of35
preliminary plans for the proposed highway improvement project and the utility's36
submission to the department of written confirmation acknowledging receipt of the plans;37
(2) The utility's submission to the department of plans showin g existing and proposed38
locations of facilities within a reasonable time as specified by the department in the letter39
required under paragraph (1) of this subsection; provided, howe ver, that the time40
specified by the department shall not be sooner than 30 days and shall not be greater than41
120 days. If the utility fails to submit to the department the plans within the allotted 12042
days, the department may no longer be required to pay the costs of removal, relocation,43
H. B. 1342
- 2 -
26 LC 39 4884
or adjustment as prescribed in subsection (b) of Code Section 3 2-6-170 even if those44
costs had previously been included in the contract between the department and the45
department's contractor; instead, such costs shall be borne by the utility; and46
(3) The utility's submission for department approval shall include with the plans a work47
plan in a manner and time frame established by the department's written procedures and48
instructions. No work plan shall be approved when, in the reas onable opinion of the49
department, it causes a highway improvement project to be delay ed beyond the50
completion time frames established by the department. If the u tility fails to submit an51
acceptable work plan, the department shall give the utility written notice that if the utility52
fails to submit an acceptable work plan within 30 days, the dep artment will let the53
proposed highway improvement project. The utility may be liable to the department or54
its contractors for costs incurred by the department or its contractors for failure of a utility55
to provide an acceptable work plan to the department. If the utility does not thereafter56
begin removal, relocation, or adjustment within the time specified in the work plan, the57
department may give the utility a final notice directing that such removal, relocation, or58
adjustment shall commence not later than ten days from the receipt of such final notice. 59
If such utility does not, within ten days from receipt of such final notice, begin to remove,60
relocate, or adjust the facility or, having so begun removal, r elocation, or adjustment,61
thereafter fails to complete the removal, relocation, or adjust ment within the time62
specified in the work plan, the department may exercise its rig ht to obtain injunctive63
relief as provided in Code Section 32-6-175. If utility removal, relocation, or adjustment64
work is found necessary after the letting date of the highway i mprovement project, the65
utility shall provide a revised work plan within 30 calendar days after becoming aware66
of such additional work or upon receipt of the department's written notification advising67
of such additional work. The utility's revised work plan shall be reviewed by the68
department to ensure compliance with additional work. Once the removal, relocation, or69
adjustment of a facility has started, if such removal, relocation, or adjustment falls behind70
H. B. 1342
- 3 -
26 LC 39 4884
schedule by 20 percent or more than set forth in the approved work plan, the department71
shall suspend the permit of such utility until such removal, re location, or adjustment72
progresses to at least 80 percent or more of the schedule set forth in the approved work73
plan.74
(c) In addition to the foregoing, the owner of the utility may shall be responsible for and75
liable to the department or its contractors for documented damages resulting solely from76
failure on the part of the utility to comply with requirements of the submitted and approved77
work plan under the control of the utility. If the utility owner fails to provide a work plan78
or fails to complete the remova l, relocation, or adjustment of its facilities in accordance79
with the work plan approved by the department, then the utility owner may shall be liable80
to the contractor for delay costs incurred by the contractor and approved by the department81
which are caused by or which grow out of the failure of the utility owner to carry out and82
complete its work in accordance with the approved work plan or in a timely and reasonable83
manner if a work plan or revised work plan was not submitted. Upon notification in84
writing by the department or its contractors that the utility is liable for damages or delay85
costs, the utility company shall have 45 days from receipt of such letter to either pay the86
amount of the damages or delay costs to the department or its c ontractors or to request87
mediation as provided in subsection (d) of this Code section. A utility owner shall not be88
subject to the damages or delay costs authorized by this subsection when the utility owner89
contracts with and reimburses the department to incorporate the removal, relocation, or90
adjustment of such utility owner's facilities into the departme nt's contract for the91
development or construction of the highway improvement project.92
(d) The department's utility relocation procedures shall inclu de, in addition to the93
provisions set forth in subsection (b) of this Code section, provisions for the establishment94
of mediation boards to hear and decide disputes that may arise between the department and95
the utility concerning (i) a work plan or revised work plan that has been submitted by the96
utility but not approved by the department; (ii) a contractor's claim for delay costs or other97
H. B. 1342
- 4 -
26 LC 39 4884
damages related to the utility's removal, relocation, or adjustment of its facilities; and (iii)98
any other matter related to the removal, relocation, or adjustment of the utility's facilities99
pursuant to this Code section. Such procedures shall include b ut not be limited to the100
following:101
(1) Each mediation board shall consist of one mediator who shall be designated by the102
department, one mediator who shall be designated by the utility , and an independent103
mediator who shall be mutually selected by the department's des ignee and the utility's104
designee and shall serve as the presiding officer of the mediation board;105
(2) The mediators shall hold a hearing with regard to each dis pute that is submitted to106
the mediation board for resolution, shall provide notice of the hearing to each party107
involved in the dispute, and shall afford each party an opportunity to present evidence at108
the hearing; provided, however, that unless the parties otherwise agree, the provisions of109
Code Sections 50-13-13, 50-13-14, and 50-13-15, relating to proceedings in a contested110
case under the Georgia Administrative Procedure Act, shall not apply to the hearing111
before the mediation board;112
(3) The mediators shall decide each issue presented to the mediation board by a majority113
vote of the mediators;114
(4) The mediators shall issue a final decision in writing with regard to each dispute that115
is submitted to the mediation board for resolution and shall se rve a copy of the final116
decision on each party involved in the dispute; and117
(5) All final decisions of the mediation board shall be subject to de novo review in the118
Superior Court of Fulton County by way of a petition for judici al review filed by the119
department or the utility within 30 days after service of the final decision.120
(e) The department shall promulgate reasonable regulations gov erning the mediation121
board, including the procedural rules governing the mediation of a contested case and the122
creation of a list of qualified mediators. The department shal l consult with the Georgia123
H. B. 1342
- 5 -
26 LC 39 4884
Utilities Coordinating Council in the development of these regu lations, and these124
regulations shall be adopted by the department on or before January 1, 2008."125
SECTION 2.126
All laws and parts of laws in conflict with this Act are repealed.127
H. B. 1342
- 6 -