Sec. 18-236. Required to comply with technical codes.
About this text
- As published by Municode, retrieved 2026-11-11
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
The building official upon notification from the permit holder or his agent shall make the following inspections and such other inspections as necessary, and shall either release that portion of the construction or shall notify the permit holder or his agent of any violations which must be corrected in order to comply with the technical codes:
(1) Building code.
a. Foundation. The foundation inspection is to be made after trenches are excavated and forms erected.
b. Frame. The frame inspection is to be made after the roof, all framing, fire blocking and bracing are in place, all concealing wiring, all pipes, chimneys, ducts and vents are complete.
c. Final. The final inspection is to be made after the building is completed and ready for occupancy.
(2) Electrical code.
a. Underground. The underground inspection is to be made after trenches or ditches are excavated, conduit or cable installed, and before any backfill is put in place.
b. Rough-in. The rough-in inspection is to be made after the roof, framing, fire blocking and bracing is in place and prior to the installation of wall or ceiling membranes.
c. Final. The final inspection is to be made after the building is complete, all required electrical fixtures are in place and properly connected or protected, and the structure is ready for occupancy.
(3) Plumbing code.
a. Underground. The underground inspection is to be made after trenches or ditches are excavated, piping installed, and before any backfill is put in place.
b. Rough-in. The rough-in inspection is to be made after the roof, framing, fire blocking and bracing is in place and all soil, waste and vent piping is complete, and prior to this installation of wall or ceiling membranes.
c. Final. The final inspection is to be made after the building is complete, all plumbing fixtures are in place and properly connected, and the structure is ready for occupancy. (See section 311 of the standard plumbing code for required tests.)
(4) Mechanical code.
a. Underground. The underground inspection is to be made after trenches or ditches are excavated, underground duct and fuel piping installed, and before any backfill is put in place.
b. Rough-in. The rough-in inspection is to be made after the roof, framing, fire blocking and bracing are in place and all ducting, and other concealed components are complete, and prior to the installation of wall or ceiling membranes.
c. Final. The foundation inspection is to be made after the building is complete, the mechanical system is in place and properly connected, and the structure is ready for occupancy.
(5) Gas code.
a. Rough piping. The rough piping inspection is to be made after all new piping authorized by the permit has been installed, and before any such piping has been covered or concealed or any fixtures or gas appliances have been connected.
b. Final piping. The final piping inspection is to be made after all piping authorized by the permit has been installed and after all portions which are to be concealed by plastering or otherwise have been so concealed, and before any fixtures or gas appliances have been connected. This inspection shall include a pressure test.
c. Final. The final inspection is to be made on all new gas work authorized by the permit and such portions of existing systems as may be affected by new work or any changes in order to ensure compliance with all the requirements of this Code and to ensure that the installation and construction of the gas system is in accordance with reviewed plans.
(6) Energy code.
a. Foundation. The foundation inspection is to be made before slab concrete is poured in place. To verify that perimeter insulation has been installed correctly on any slab on grade foundations, if required.
b. Frame. The frame inspection is to be made before exterior wall insulation is concealed by wall board to check installation of exterior walls insulation and to inspect that all holes and cracks through the structure envelope have been sealed in an appropriate manner as to restrict air passage.
c. Final. The final inspection is to be made after the building is completed and ready for occupancy. To verify installation and R-value of ceiling and floor insulation. To verify correct SEER ratings on appliances.