32-2-78. Definitions.

The only printed version. Current through: Including Acts of the 2025 Regular Session of the General Assembly.

As used in this part, the term: (1) “Alternative contracting method” means a method of contracting authorized by Code Section 32-2-82. (2) “Construction manager/general contractor” means a person the department has selected to perform project delivery pursuant to Code Section 32-2-82. (3) “Participating local governing authority” includes the governing authority of any county or municipality whose geographical jurisdiction includes the project. (4) “Project” means an undertaking, including intermodal railrelated and multimodal transportation solutions, which the department deems appropriate for pursuing or letting based upon the authority granted in this part.