Title 46. PUBLIC UTILITIES AND PUBLIC TRANSPORTATION · Chapter 5. TELEPHONE SERVICE · Article 2. TELEPHONE SERVICE · Part 2. CONSTRUCTION AND OPERATION OF LINES, PLANTS, OR SYSTEMS GENERALLY
46-5-41. Obtaining of certificate of public convenience and necessity for construction, operation, acquisition, or extension of telephone lines, plants, or systems.
Current through: Including Acts of the 2025 Session of the General Assembly of Georgia.
No person shall construct or operate any telephone line, plant, or system or any extension thereof or acquire ownership or control thereof, either directly or indirectly, without first obtaining from the commission a certificate that the present or future public convenience and necessity require or will require such construction, operation, or acquisition.
History
Ga. L. 1950, p. 311, § 1; Ga. L. 2012, p. 847, § 9/HB 1115; Ga. L. 2025, p. 1029, § 46(70)(L)/SB 153, effective July 1, 2025.
Amendments
The 2025 amendment, effective July 1, 2025, part of an Act to revise, modernize, and correct the Code, substituted “commission” for “Public Service Commission”.
Read the official page (the state's PDF, opened at the page this text was read from).
Current through: Including Acts of the 2025 Session of the General Assembly of Georgia.
Text read from t46-(v34)-2025-pdf.pdf, Volume V34, 2025 edition, page 551; merge action: bound only; file SHA-256 53ab60ae5027.
Ask about this section
The answer is drawn from this section and, when they fit, the other sections of its chapter. It quotes the text and names the section for each claim. Not legal advice.