8-2-39. Discovery of additional defects after original notice given.
Current through: Including Acts of the 2025 Regular Session of the General Assembly.
- (a)
A construction defect that is discovered after a claimant has provided a contractor with the initial claim notice may not be alleged in an action until the claimant has given the contractor who performed the original construction:#
- (b)
A construction defect that is discovered during the pendency of an action filed in compliance with this part may be added as a supplemental or additional claim to the pending action if failure to add the claim would prejudice any legal rights of the claimant or the contractor; provided, however, that the claimant shall comply with the requirements of subsection (a) of this Code section, and such action shall be immediately stayed until completion of the notice of claim process, unless otherwise agreed by the parties.#
History
Code 1981, § 8-2-39, enacted by Ga. L. 2004, p. 500, § 1; Ga. L. 2006, p. 548, § 1/SB 573.
Editor's notes
Ga. L. 2006, p. 548, § 3(c)/SB 573, not codified by the General Assembly, provides that the amendment to this Code section shall only apply with respect to causes of action or claims arising on or after April 28, 2006, and any prior causes of action or claims shall continue to be governed by prior law.
Read the official page (the state's PDF, opened at the page this text was read from).
Current through: Including Acts of the 2025 Regular Session of the General Assembly.
Text read from t7-t8-(v5)-2024-pdf.pdf, Volume V5, 2024 edition, pages 896 to 897; merge action: carried; file SHA-256 5c69f28428d8.