Title 9. CIVIL PRACTICE · Chapter 3. LIMITATIONS OF ACTIONS · Article 3. LIMITATIONS ON RECOVERY FOR DEFICIENCIES CONNECTED WITH IMPROVEMENTS TO REALTY AND RESULTING INJURIES
9-3-50. Definitions.
Current through: Including Acts of the 2025 Regular Session of the General Assembly.
As used in this article, the term:
- (1)
“Person” means an individual, corporation, partnership, business trust, unincorporated organization, association, or joint-stock company.#
- (2)
“Substantial completion” means the date when construction was sufficiently completed, in accordance with the contract as modified by any change order agreed to by the parties, so that the owner could occupy the project for the use for which it was intended.#
History
Ga. L. 1968, p. 127, §§ 5, 6.
Read the official page (the state's PDF, opened at the page this text was read from).
Current through: Including Acts of the 2025 Regular Session of the General Assembly.
Text read from t9-ch1-10-(v6)-2023-pdf.pdf, Volume V6, 2023 edition, page 299; merge action: carried; file SHA-256 ea8a520ad52f.
Ask about this section
The answer is drawn from this section and, when they fit, the other sections of its chapter. It quotes the text and names the section for each claim. Not legal advice.