Acworth · Zoning Ordinance

Appendix B - ZONING ORDINANCE

73-7.7.3. Standards for All Wireless Communications Uses.

About this text

  • As published by Municode, current through 2026-02-09
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

A. Wireless communication facilities are allowed in accordance with Section 73-4.4 Use Table. In addition, the following activities are permitted as of right in all districts:

1. Removal or replacement of transmission equipment on an existing wireless support structure that does not result in a substantial modification of the wireless communication facility; and,

2. Ordinary maintenance of existing wireless communication facilities and wireless support structures; and,

3. Distributed antenna systems when located within a building or on the exterior of a building.

B. Removal of Abandoned Antenna and Towers. Any wireless support structure that is not actively used by wireless carriers for a continuous period of six (6) consecutive months will be considered abandoned, and the owner of the wireless support structure shall remove it within 60 days of receiving written notice from the City. The City shall ensure and enforce removal by means of its existing regulatory authority, with costs of removal charged to the owner.

C. Existing Towers and Antennas. Wireless telecommunication facilities lawfully existing on or before the effective date of this Zoning Ordinance are allowed to remain in place and continue in use and operation. Ordinary maintenance and co-location is permitted, provided than any substantial modification requires review and approval in accordance with the special use procedures of Section 73-11.7 Special Use Permits.

D. Safety standards. To ensure the structural integrity of communication structures, the owner of a structure shall ensure that it is maintained in compliance with standards contained in applicable local building codes and the applicable standards for towers that are published by the Electronic Industries Association, as amended from time to time. Tower owners shall conduct periodic inspections of communication towers at least once every three years to ensure structural integrity. Inspections shall be conducted by a structural engineer licensed to practice in the State.

E. Regulatory compliance. All structures and facilities shall meet or exceed current standards and regulations of the FAA, the FCC, and any other agency of the state or federal government with the authority to regulate communications towers and antennas. If such standards and regulations are changed then the owners of the communications towers and antennas into compliance with such revised standards and regulations within six (6) months of the effective date of such standards and regulations, unless a more stringent compliance schedule is mandated by the controlling federal agency.

F. Lighting. No illumination is permitted on an antenna or tower unless required by the FCC, FAA, or other State or federal agency of jurisdiction, in which case the Development Director shall review the available lighting alternatives and approve the design that would cause the least disturbance to the surrounding uses and views.

G. Signage. No signage is permitted on a facility or structure, except Official Signs as defined in the Sign Ordinance.

H. Visual impact.

1. Structures shall either maintain a galvanized steel finish or subject to any applicable standards of the FAA or other applicable federal or state agency, or be painted a neutral color, so as to reduce visual obtrusiveness.

2. At a structure site, the design of the buildings and related structures shall, to the extent possible, use materials, colors, textures, screening, and landscaping that will blend the tower facilities to the natural setting and built environment.

I. Decisions.

1. The environmental effects of radio frequency emissions may not serve as a basis to approve, deny, or otherwise regulate a telecommunication facility to the extent that emissions comply with Federal Communications Commission regulations.

2. All decisions denying a request to place, construct, or modify a wireless communication use must be in writing and be supported by a written record documenting the reasons for the denial and the evidence in support of the decision.

J. The placement of additional buildings or other supporting equipment necessarily required in connection with an otherwise authorized wireless communication use is specifically authorized.

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:acworth/zoning/73-7.7.3@2026-02-09-a55c4a1828

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.