Adairsville · Zoning Ordinance
Part II - CODE OF ORDINANCES / Chapter 47 - ZONING / Article XI - ENFORCEMENT
Sec. 47-279. Permits and applications.
About this text
- As published by Municode, current through 2026-08-20
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
(a) A permit is required to collocate a small wireless facility in the public right of way or to install, modify, or replace a pole or a decorative pole in the public right of way. A permit is not required to perform the activities described in O.C.G.A. § 36-66C-6(e) or (f).
(1) The collocation can be on or adjacent to a pole, decorative pole, or a support structure.
Poles and decorative poles by definition are in the right of way, and support structures may be located outside of the right of way. However, permitting support structures is not part of this process.
(b) Any person seeking to collocate a small wireless facility in the public right of way or to install, modify, or replace a pole or a decorative pole in the public right of way shall submit an application to the city community development director for a permit. Applications are available from the community development director. The application template is included as exhibit A to the ordinance from which this section derived, and the application requirements are listed below in subsection 47-279(d) of this article. Any material change in information contained in an application shall be submitted in writing to the community development director for the city within 30 days after the events necessitating the change.
(c) Each application for a permit shall include the maximum application fees: $100.00 per existing pole, $250.00 per replacement pole, and $1,000.00 per new pole as permitted under O.C.G.A. § 36-66C-5(a)(1), (a)(2) and (a)(3). Such maximum application fees shall automatically increase by 2.5 percent annually on January 1 of each year beginning January 1, 2021, as provided under O.C.G.A. § 36-66C-5(b).
(1) If the FCC issues an order regarding fees that is overturned or modified, the SWFAA fees are capped at what is determined to be "fair and reasonable."
(d) Applications shall be made by the applicable wireless provider or its duly authorized representative and shall contain the following:
(1) The applicant's name, address, telephone number, and email address, including emergency contact information for the applicant;
(2) The names, addresses, telephone numbers, and email addresses of all consultants, if any, acting on behalf of the applicant with respect to the filing of the application;
(3) A general description of the proposed work and the purposes and intent of the proposed facility. The scope and detail of such description shall be appropriate to the nature and character of the physical work to be performed, with special emphasis on those matters likely to be affected or impacted by the physical work proposed;
(4) Detailed construction drawings regarding the proposed use of the right of way;
(5) To the extent the proposed facility involves collocation on a pole, decorative pole, or support structure, a structural report performed by a duly-licensed engineer evidencing that the pole, decorative pole, or support structure will structurally support the collocation, or that the pole, decorative pole, or support structure may and will be modified to meet structural requirements, in accordance with applicable codes;
(6) For any new aboveground facilities, visual depictions or representations if such are not included in the construction drawings;
(7) Information indicating the horizontal and approximate vertical location, relative to the boundaries of the right of way, of the small wireless facility for which the application is being submitted;
(8) If an application is reasonable and does not impose technical limitations or significant additional costs and the pole or replacement decorative pole applied for cannot be collocated on an existing pole or support structure in which the wireless provider has the right to collocate. The wireless provider shall certify that it has made such a determination in good faith, based on the assessment of a licensed engineer, and shall provide a written summary of the basis for such determination;
(9) If the small wireless facility will be collocated on a pole or support structure owned by a third party, other than an authority pole or a decorative pole, a certification that the wireless provider has permission from the owner to collocate on the pole or support structure; and
(10) If the applicant is not a wireless services provider, a certification that a wireless services provider has requested in writing that the applicant collocate the small wireless facilities or install, modify, or replace the pole or decorative pole at the requested location.
(e) The community development director for the city shall review applications for permits according to the timelines and using the procedures identified in O.C.G.A. § 36-66C-7 and section 47-279 of this article for review of applications and O.C.G.A. § 36-66C-13 for consolidated applications.
(f) Within 20 days of receipt of a written application, the community development director in good faith shall:
(1) Notify the applicant in writing of the commencement and completion dates of any widening, repair, reconstruction, or relocation of the applicable right of way that is scheduled to commence, or is anticipated in good faith to commence, within 24 months after the application is filed;
(2) Notify the applicant of any aspect of the application that appears to be grounds for the authority's denial of the application pursuant to subsection (o) of this section; and
(3) Determine whether the application is complete and inform the applicant of its determination in writing.
(g) If the community development director determines that an application is incomplete, it shall specifically identify to the applicant in writing all missing information within such 20-day period; otherwise the application is deemed complete;
(1) If the community development director identifies missing information to the applicant as provided in this paragraph, the applicant may submit such missing information to the authority within 20 days of receipt of notification in writing from the authority that the application is incomplete without paying any additional application fee, and any subsequent review of the application by the authority for completeness shall be limited to the previously identified missing information;
(2) If the community development director determines that an application remains incomplete, or if the authority determines that the applicant has made material changes to the application other than to address the missing information identified by the authority, the authority shall notify the applicant of such determination in writing within ten days of receipt of the resubmission of the written application, and absent an agreement to the contrary between the authority and the applicant that is confirmed by email or other writing, such notice shall constitute a denial of the application; and
(3) If the community development director does not provide such written notification to the applicant within this ten-day period, the application shall be deemed complete.
(h) The community development director shall make its final decision to approve or deny the application within 30 days of the written determination that the application is complete or when the application is deemed complete under this section, whichever is earlier, for a collocation, and within 70 days of the written determination that the application is complete or when the application is deemed complete under this section, whichever is earlier, for the installation, modification, or replacement of a pole or decorative pole.
(i) A decision to deny an application pursuant to this section shall be in writing, shall identify all reasons for the denial, and shall identify the provisions of applicable codes or other standards applicable pursuant to this section. The decision to deny shall be sent contemporaneously and will not end the review period until its decision is delivered to the applicant.
(j) If the community development director fails to act on an application within the applicable review period, the applicant may submit to them a written notice that the time period has lapsed. The notice gives the community development director 20 days, after receipt of notice, to render its written decision. If the city does not render a written decision, then the application shall be deemed approved.
(k) If an area is designated solely for underground or buried facilities of communications and electric service providers, then the service providers must not install poles in a right of way above ground unless the wireless providers seek a waiver of the underground requirement for placement of a new pole to support small wireless facilities consistent with applicable law.
(l) A city that adopts undergrounding requirements shall allow a wireless provider to maintain in place any previously collocated small wireless facilities subject to any applicable pole attachment agreement or to allow the wireless provider to replace the pole previously collocated at the same location or to propose an alternate location within 50 feet of the prior location, unless the alternate location imposes technical limits or significant additional cost.
(m) A permit from the city does not grant the applicant a license or authorization to impinge upon the rights of others that may already have an interest in the right of way. The collocation, installation, modification, or replacement for which a permit is issued shall be completed within six months after issuance:
(1) An extension shall be granted for up to an additional six months upon written request made to the authority before the end of the initial six-month period if a delay results from circumstances beyond the reasonable control of the applicant.
(n) Applications for permits shall be approved except as follows:
(1) In order to receive a permit to install a pole or replace a decorative pole, the applicant must have determined after diligent investigation that it cannot meet the service objectives of the permit by collocating on an existing pole or support structure on which:
a. The applicant has the right to collocate subject to reasonable terms and conditions; and
b. Such collocation would not impose technical limitations or significant additional costs.
The applicant shall certify that it has made such a determination in good faith, based on the assessment of a licensed engineer, and shall provide a written summary of the basis for such determination.
(2) The community development director may deny an application for a permit upon any of the conditions identified in O.C.G.A. § 36-66C-7(j) as described subsection 47- 279(o) of this article.
(3) For applications for new poles in the public right of way in areas zoned for residential use, the community development director may propose an alternate location in the public right of way within 100 feet of the location set forth in the application, and the wireless provider shall use the community development director's proposed alternate location unless the location imposes technical limits or significant additional costs. The wireless provider shall certify that it has made such a determination in good faith, based on the assessment of a licensed engineer, and it shall provide a written summary of the basis for such determination.
(o) An application for permitted uses as described in O.C.G.A § 36-66C-6 shall be approved unless the requested collocation of a small wireless facility or requested installation, modification, or replacement of a pole or decorative pole:
(1) Interferes with the operation of traffic control equipment; with sight lines or clear zones for transportation or pedestrians;
(2) Fails to comply with the federal Americans with Disabilities Act, 42 U.S.C. § 12101 et seq., or similar laws of general applicability regarding pedestrian access or movement;
(3) Requests that ground-mounted small wireless facility equipment be located more than
7.5 feet in radial circumference from the base of the pole, decorative pole, or support structure to which the small wireless facility antenna would be attached, provided that the authority shall not deny the application if a greater distance from the base of the pole, decorative pole, or support structure is necessary to avoid interfering with sight lines or clear zones for transportation or pedestrians or to otherwise protect public safety;
(4) Fails to comply with the maximum limitations for fees set forth in O.C.G.A § 36-66C6(h) or the requirements of O.C.G.A § 36-66C-6(i) regarding exclusive arrangements;
(5) If an application to install a pole or decorative pole interferes with the widening, repair, reconstruction, or relocation of a public road or highway by an authority or the department of transportation that has been advertised for bid and scheduled for completion within six months after the application is filed;
(6) If an application to install a pole or decorative pole interferes with a public works construction project governed by O.C.G.A. tit. 36, ch. 91 and scheduled for completion within six months after the application is filed;
(7) Fails to comply with O.C.G.A § 36-66C-10 regarding historic districts, O.C.G.A § 36- 66C-11 regarding alternate locations in right of way, and O.C.G.A § 36-66C-12 regarding decorative pole replacements;
(8) Fails to comply with laws of general applicability that are not inconsistent with O.C.G.A § 36-66C, that address pedestrian and vehicular traffic, safety requirements, or the occupancy or management of the right of way.
(p) A permit issued under this article shall authorize such person to occupy the public rights of way to:
(1) Collocate a small wireless facility on or adjacent to a pole or a support structure that does not exceed the height limitations set forth in O.C.G.A. § 36-66C-7(h)(3) or on or adjacent to a decorative pole in compliance with O.C.G.A. § 36-66C-12; and
(2) Install, modify, or replace a pole or decorative pole for collocation of a small wireless facility that does not exceed the height limitations set forth in O.C.G.A. § 36-66C7(h)(1) and (h)(2).
(q) Upon the issuance of a permit under this section, and on each anniversary of such issuance, every person issued a permit shall submit to the city the maximum annual payments permitted under O.C.G.A. § 36-66C-5(a)(4) and (a)(5); provided, however, that if such person removes its small wireless facilities from the public rights-of-way pursuant to O.C.G.A.
§ 36-66C-5(e), then such person shall be responsible for the pro rata portion of the annual payment based on the number of days of occupation since the last annual payment. Upon making such pro rata payment and removal of the small wireless facilities, the person's annual payment obligations under this section shall cease as of the date of the actual removal. The maximum annual payments shall automatically increase on January 1 of each year beginning January 1, 2021, as provided under O.C.G.A. § 36-66C-5(b).
(r) Any person issued a permit shall pay the fees, regarding make-ready work or generally applicable nondiscriminatory fees as identified in O.C.G.A. § 36-66C-5(a)(6) and (a)(7), as applicable.
(s) The city may revoke a permit issued pursuant to this article if the wireless provider or its equipment placed in the public right-of-way under that permit subsequently is not in compliance with any provision of this article or the Georgia Streamlining Wireless Facilities and Antennas Act. Upon revocation, the city may proceed according to subsection 47-279(t).
(t) If a wireless provider occupies the public rights-of-way without obtaining a permit required by this section or without complying with the SWFAA, then the city may, at the sole discretion of the city, restore the right-of-way, to the extent practicable in the reasonable judgment of the city, to its condition prior to the unpermitted collocation or installation and to charge the responsible wireless provider the reasonable, documented cost of the city in doing so, plus a penalty not to exceed $1,000.00, as authorized under O.C.G.A. § 36-66C-6(b). The city may suspend the ability of the wireless provider to receive any new permits from the city under this section until the wireless provider has paid the amount assessed for such restoration costs and the penalty assessed, if any; provided, however, that the city may not suspend such ability of any applicant that has deposited the amount in controversy in escrow pending an adjudication of the merits of the dispute by a court of competent jurisdiction.
(u) All accepted applications for permits shall be publicly available subject to the limitations identified in O.C.G.A. § 36-66C-6(c), which state that upon a reasonable belief portions of the application may be designated as containing trade secrets.
(v) An applicant may file a consolidated application related to multiple small wireless facilities, poles or decorative poles so long as such consolidated application meets the requirements of O.C.G.A. § 36-66C-13.
(w) Activities authorized under a permit shall be completed within the timelines provided in O.C.G.A. § 36-66C-7(k)(2), which states that permits issued hereunder shall be completed within six months after issuance. An additional six-month extension shall be granted upon written request, if such written request is made prior to the end of the initial six-month period, if a delay results from circumstances beyond the reasonable control of the applicant.
(x) Issuance of a permit authorizes the applicant to:
(1) Undertake the collocation, installation, modification or replacement approved by the permit; and
(2) Operate and maintain the small wireless facilities and any associated pole covered by the permit for a period of at least ten years.
(y) Permits shall be renewed following the expiration of the minimum ten-year term and upon the terms and conditions identified in O.C.G.A. § 36-66C-7(k)(2)(B) regarding grounds for denial of applications and the widening, repair, reconstruction, or relocation of roads, poles, support structures, or small wireless facilities.
(z) If an application for a permit seeks to collocate small wireless facilities on authority poles in the public rights of way, then the city shall, within 60 days of receipt of the completed application:
(1) Provide a good faith estimate for any make-ready work necessary to enable the authority pole to support the proposed facility; or
(2) Notify the wireless provider that the wireless provider will be required to perform the make-ready work.
Any make-ready work performed by the city shall be completed within 90 days of receipt of written acceptance of the good faith estimate by the wireless provider. Such acceptance shall be signified by payment of check or other commercially reasonable and customary means pursuant to and in accordance with the provisions of O.C.G.A. § 36-66C-7(n).
History
(Ord. No. 2019-0009, § 6, 11-14-2019)
Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.