--- title: Avondale Estates Zoning Ordinance, Sec. 21-6.2.6. EV readiness collection: local-codes id: local-code:avondale-estates/zoning/21-6.2.6 cite_as: Avondale Estates, Ga., Zoning Ordinance ยง 21-6.2.6 canonical_url: https://georgiacommons.org/code/local/avondale-estates/zoning/21-6.2.6 md_url: https://georgiacommons.org/code/local/avondale-estates/zoning/21-6.2.6.md text_url: https://georgiacommons.org/code/local/avondale-estates/zoning/21-6.2.6/text source_url: https://library.municode.com/ga/avondale_estates/codes/code_of_ordinances date: 2024-04-17 status: active jurisdiction: city:avondale-estates jurisdiction_name: Avondale Estates place_fips: "1304644" corpus_version: local-codes-avondale-estates-7a4d79de2159 publisher: Georgia Commons, an independent project of Georgia Civic Data. Not the State of Georgia. Not legal advice. up: https://georgiacommons.org/code/local/avondale-estates/zoning/~appendix-a/~chapter-21/~article-6/~division-6.2.md previous: https://georgiacommons.org/code/local/avondale-estates/zoning/21-6.2.5.md next: https://georgiacommons.org/code/local/avondale-estates/zoning/21-6.2.7.md index: https://georgiacommons.org/code/local/avondale-estates.md branch: zoning edition: As published by Municode, current through 2024-04-17 edition_date_kind: current_through source_publisher: Municode version_id: local-code:avondale-estates/zoning/21-6.2.6@2024-04-17-ef5e44b368 --- # Avondale Estates Zoning Ordinance, Sec. 21-6.2.6. EV readiness > As published by Municode, current through 2024-04-17 > The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included. Part of: Appendix A / Chapter 21 - ZONING ORDINANCE / Article 6 - SITE DEVELOPMENT FEATURES / Division 6.2 - PARKING AND ACCESS All new developments in any commercial, mixed-use, and MF-zoned districts are required to provide electric vehicle supply equipment (EVSE) infrastructure to accommodate the future installation of electric vehicle supply equipment. The infrastructure shall be provided per this section. A. The EVSE infrastructure shall be installed per the requirements of the current edition of the National Electrical Code (NFPA 70), as adopted and amended by the State of Georgia . 1. The off-street parking provided shall have EVSE infrastructure installed at the parking spaces dedicated for the use of the building. 2. The ratio of electric vehicle parking spaces to non-electrical vehicle parking spaces shall be 1:5, and only applies to the total new parking spaces. B. All new off-street parking, or the expansion of existing off-street parking for buildings shall include EVSE infrastructure based on the total number of parking spaces established in section 21-6.2.6.A.2. C. The EVSE infrastructure shall include a raceway, which is continuous from the branch circuit/feeder panel location to the future PHEV/EV parking space. The raceway shall be sized and installed per the National Electrical Code; however, in no case, shall the EVSE infrastructure raceway be less than one (1) inch in size. The EVSE infrastructure raceway shall include a pull rope or line installed for future conductor installation, with the raceway sealed and labeled for future use. D. The electrical equipment room, shall have a dedicated space for the future installation of EVSE. This space shall be identified on all construction documents submitted for review, and the dedicated space shall not allow for violation of the National Electrical Code prescriptive requirements regulating working space clearances around equipment, or violation of the National Electrical Code prescriptive requirements governing the entrance to and egress from electrical equipment working space. E. During construction of the electrical equipment room, all raceways installed for the EVSE infrastructure shall terminate at the space dedicated for the future EVSE installation. F. Prior to the final electrical inspection approval, the space dedicated within the electrical equipment room for the future EVSE installation shall have the wall stenciled or marked legibly with the following text: "Future electric vehicle charging equipment and panels." G. The placement of EVSE shall not create a trip hazard or violation of the accessible path of travel when the cord is connected to an EV or PHEV.