(a) Request for design exception. When unique conditions and circumstances exist on a project, the developer's engineer may submit a request for design exception in a format provided by the director of public works. Design exceptions request should be identified as early as possible during the design process. The director of public works is the approval authority for design exceptions. (b) Field changes. Minor changes in construction plans caused by field conditions shall be made at the direction of the director of public works with the cost of such changes to be paid by the developer. All changes are to be documented as revisions to the approved development plans and correctly shown on the as-built surveys. Discrepancies between the as-built surveys and the approved development plans may result in delays in approving final plats or certificates of occupancy.