(a) Utility easements.
(1) Utility easements for private utilities shall be avoided except in cases where no other satisfactory arrangements can be provided for the installation of private utilities.
(2) Whenever it is necessary or desirable to locate a public utility line outside of the street right-of-way, the line shall be located in an easement dedicated to the county (or other appropriate public entity) for such purpose. Easements for water and sanitary sewers shall be a minimum of 20 feet wide, and may be required to be wider depending on the depth of cut to maintain a 1:1 open cut slope. When warranted, temporary construction easements widths shall be as required by the county.
(3) Easements for sanitary sewers may be required by the director of public works for future extension of lines, whether or not the subdivision or development is currently proposed to be served by public sewer.
(b) Pedestrian easements. Pedestrian easements, not less than ten feet wide, may be required where deemed essential to provide circulation, or access to schools, playgrounds, shopping centers, transportation, and other community facilities.
(c) Drainage and access easements.
(1) Publicly dedicated drainage easements for improved ditches, pipe construction, and detention facilities shall be cleared, opened, and stabilized at the time of development to control surface water runoff. Runoff slopes and side slopes shall be specified by the developer's engineer according to good engineering practices.
(2) Publicly dedicated drainage easements shall be provided where a development is traversed by or contains a watercourse, impoundment, detention pond, floodplain, natural stream or channel. It shall conform substantially to the flooding limits of the 100-year storm along such natural drainage feature, but shall not be less than 20 feet in width.
(3) A publicly dedicated drainage easement is to be provided along any manmade drainage channel or drainage pipe located outside a street right-of-way. All drainage easements shall be calculated as the pipe diameter plus two feet plus two times the depth, rounded up to the nearest five-foot interval, but shall be no less than 20 feet wide.
(4) Drainage easements outside of the street right-of-way shall be clearly defined on the final plat with dimensions or bearings and distances as appropriate. Approval of a plat by the county shall not constitute acceptance of any easement indicated on the plat by the county; absent express acceptance by the county all easements shall be considered dedicated to the public and not accepted by the county. The property owner will be required to maintain and keep the publicly-dedicated easement free of obstruction in such a way as to assure the maximum designed flow at all times. The property owner shall not alter any drainage improvements without the prior approval from the county.
(5) Barrow County may access and maintain, but assumes no responsibility to maintain publicly-dedicated easements, natural or artificial drains, pipes, and other structures beyond the extent of county property and county-accepted drainage easements.
Barrow County assumes no responsibility for the extension of culverts beyond the point shown on the approved and recorded plan.
(d) Conservation and natural resource easements. Conservation and natural resource easements, as may be required by this Development Code shall be clearly defined on the plat and deed of the individual property owner, and must conform to the requirements set out for such easements in the environmental protection article of this Development Code.
(e) Overlapping easements. Easements for water, sanitary sewers and drainage purposes may be combined, but must be a minimum of 30 feet if in combination. Any easement containing more than one pipe must provide at least ten feet beyond the pipe and the pipes must be at least ten feet apart (measured on center). Wider easements shall be required when necessary to maintain a 1:1 open cut slope to each pipe.