(a) Development activity.
(1) Preconstruction activity. Following the issuance of any permit authorizing clearing and grading of a site, areas required to be undisturbed, such as natural buffers or stream greenways, must be designated and shall be inspected and approved by the planning and community development department prior to the commencement of any clearing or grading activities.
(2) Grading.
a. Grading shall be done in accordance with the lines and grades drawn on the approved grading plan.
b. Required erosion and sedimentation control measures and stormwater drainage facilities are to be installed in accordance with the approved plans as development progresses.
(b) Development phase inspections. The owner or contractor shall make requests for inspections to the planning and community development department at least 48 hours prior to when the inspection is needed. Inspections shall be made and passed prior to continuation of further activity or proceeding into new phases. Inspections are required of each of the following phases, as applicable to the actual work to be performed under the development permit:
(1) Prior to clearing or clearing and grubbing of the property or any portion included under the development permit, and after certification by the registered design professional that prepared the plan, inspection of erosion and sedimentation control measures and protective devices for undisturbed areas. Inspections of erosion and sedimentation control measures will be conducted on a continuing basis.
(2) Upon completion of street grading, inspection and approval shall be required prior to trenching or continuation with subgrade preparation.
(3) Upon installation of storm drainage pipe, detention, or other stormwater facilities, inspection and approval shall be required.
(4) Street curbing and gutter (if provided). Inspection shall be requested after the subgrade is compacted and forms or string line have been set. Street width and vertical and horizontal alignment may be spot-checked.
(5) Sub-grade of streets. After compaction and receipt of test reports by the planning and community development department (as required under subsection 89-1260(g)), the sub-grade shall be roll tested with a fully loaded 18-ton tandem dump truck (confirmed via certified weight ticket), and shall pass to the satisfaction of the development inspector. "Pass" shall be defined as no appreciable movement under the tires during proof rolling.
(6) Street base. After receipt of test reports by the planning and community development department, the base may be string-lined for depth and crown. The street base may be roll-tested with an 18-ton tandem dump truck and shall pass to the satisfaction of the public works director.
(7) Paving. A development inspector will periodically be on site during the paving process to check consistency, depth, and workmanship, as applicable. For asphalt paving, the temperature of the material will be monitored and the street will be cored by the developer after completion to check thickness and density. Coring shall be completed at an interval of one core per 500 linear feet of roadway, with no less than one core obtained in each cul-de-sac. Each core shall measure 0.25 inch of the required thickness. Testing standards are shown on Table 11.2. No average thickness evaluation will be allowed. Pavement found to be less than the required thickness shall be removed and replaced with pavement meeting the specification.
Overlay of pavement to bring the section into compliance may be allowed at the sole discretion of the director of public works. Satisfactory test results of the cores shall be delivered to the planning and community development department for review by the public works department prior to approval of a final subdivision plat or certificate of occupancy.
(c) As-built surveys.
(1) Upon completion of the development activity as authorized by the development permit and prior to final development inspection of public and private improvements, the owner shall submit to the public works department for review and approval a complete set of record drawings showing as-built conditions prepared by a registered land surveyor. The acceptance of as-built plans shall be a prerequisite to final construction acceptance, and the issuance of a final certificate of use and occupancy.
Final inspections will not be made unless the as-built plans are available. These drawings shall show the location, vertical and horizontal alignment, and finished elevations of:
a. Drainage system pipes and channels.
b. Stormwater detention facilities, including a volume survey, grading and outlet control structure details (i.e., orifice elevations, sizes, weir sizes, etc.).
c. Sanitary sewer system (if any).
d. Water system.
e. Streets, including street centerlines showing angles of deflection and standard curve data of intersection, radii, length of tangents and arcs, and degree of curvature with basis of curve data.
f. Other features as needed to fully document as-built conditions.
(2) The as-built surveys shall be certified and sealed by the registered land surveyor, subject to the tolerances of accuracy indicated in the survey certification.
(3) The as-built surveys shall be accompanied by a certified as-built hydrology report prepared by a licensed professional engineer showing that the as-built facility complies with the stormwater regulations.
(4) The as-built surveys shall be submitted in hard copy format and in a digital format acceptable by the director of public works.
(d) Final development inspection.
(1) Following submission and review of the as-built surveys and as-built hydrology report, the public works department shall conduct a final development inspection of the project.
(2) The owner shall be responsible for correcting any deficiencies identified in the final development inspection prior to approval of a final subdivision plat.
(e) Maintenance and performance guarantees.
(1) Prior to approval of a final subdivision plat, or issuance of a certificate of occupancy for a multi-family or nonresidential development project, maintenance and performance guarantees, in forms as described in this section below, are required for all public improvements shown on the as-built surveys. The owner shall be responsible for maintenance of all such public improvements for one and one-half years from the date of issuance of the certificate of occupancy or final subdivision plat approval, as applicable, and for topping of roads pursuant to subsection 89-1180(c) and (d) of Article X.
(2) The value of the maintenance guarantee shall be equal to 33 percent of the actual cost of construction of the public improvements shown on the as-built surveys.
Copies of contractor agreements or actual invoices paid, or as otherwise determined by the public works director, shall evidence the cost of construction. The value of the performance guarantees shall be determined in accordance with subsection 89-1180(c) and (d) of Article X.
(3) Repairs shall be made for any deficiencies identified within the bonding period of the guarantees or the guarantees shall be called upon to complete same.
(4) Any guarantee required pursuant to this article shall be in one of three forms: 1) in a form provided by the county and by a surety in good standing with the Georgia Insurance and Fire Safety Commissioner's Office and listed in Circular 570 (Federal Register Vol. 62, No. 126) among companies holding certificates of authority as acceptable sureties on federal bonds and as acceptable reinsuring companies; 2) a cash guarantee in a form provided by the county; or 3) an irrevocable letter of credit or commitment upon which the county can draw from a bank or other financial institution in a form acceptable to the county. These three options are referred to collectively herein as the "guarantees."
(5) A maintenance guarantee for the water system improvements and the sanitary facilities may be required separately by the authority having jurisdiction, in accordance with their regulations. For both the water system and sewer system improvements, the developer shall be responsible for maintenance of all water and sewer mains and appurtenances for one year from the date of approval of the certificate of development conformance by correcting all defects or deficiencies in materials and workmanship.
(6) In cases where the maintenance and performance guarantees are to cover a second phase or any other later stage of a development project governed by this article, said guarantees shall be required to be extended in amount and application to cover the original phase of the project in addition to said later phase for the same period of application as set out in this Development Code if the later phase will utilize the same entrance-street as that used by the original phase of the project.
(7) The maintenance guarantee shall include the estimated cost for maintenance of the drainage and detention pond facilities during the one and one-half-year maintenance period. Maintenance shall include repair of erosion controls, removal of silt from detention ponds and other items pertinent to the drainage system for each development.
(8) In the event the development has not completed at least 90 percent build out by the end of the original guarantee period, the guarantee shall be renewed in 18-month intervals until 90 percent build out is achieved (i.e. certificate of occupancy is issued on 90 percent of the homes).
(9) When all of the following four conditions are met, this subsection (9) shall apply:
a. A final subdivision plat has been approved;
b. The original owner of the subdivision at the time of approval of the subdivision plat no longer owns any lots in said subdivision, has filed for bankruptcy, or is otherwise determined to be insolvent;
c. Either no maintenance guarantee or performance guarantee is in place for the subdivision; and
d. More than one person or entity owns undeveloped lots (i.e. lots without a certificate of occupancy) in said subdivision such that posting of a guarantee(s) for the entire subdivision is not feasible.
In the event of the fulfillment of the above-stated four conditions, the county may, in its discretion, accept from the applicant for a building permit or for a certificate of occupancy for any lot or series of lots, a cash guarantee in the amount of a by-lot, pro-rata portion of the amount of the applicable guarantee that would otherwise be required for the entire subdivision, in lieu of the guarantees required to provide for maintenance and performance requirements for the entire subdivision. By way of example, in a 100-lot subdivision for which the normal required maintenance guarantee would be $10,000.00 and the normal performance guarantee would be $20,000.00, an applicant for one lot could provide a cash maintenance guarantee in the amount of $100.00 and a cash performance guarantee in the amount of $200.00; an applicant for two lots could provide a cash maintenance guarantee in the amount of $200.00 and a cash performance guarantee in the amount of $400.00. This subsection (9) is intended to apply only in exceptional circumstances where neither the original subdivision owner nor their successor in interest exists or is solvent and multiple builders have purchased lots in the subdivision, and only in order for the county to ensure a funding source for the maintenance and performance costs associated with the subdivision.
(f) Abandoned projects.
(1) A development permit shall expire by limitation and shall become null and void if the project has not been completed and the final plat issued within five years of approval of such permit. The planning and community development director may grant a one year extension provided such extension is requested by the permit holder in writing prior to expiration of the permit and justifiable cause is demonstrated.
(2) Projects with expired permits may re-apply for consideration under the standards in effect at the time of re-submission.
(3) Any project whose permit has lapsed under the terms expressed in this Development Code shall immediately proceed to stabilize all disturbed areas. This responsibility shall fall upon the owner, developer, contractor, or any and all.