Sec. 89-1259. Installation of stormwater drainage facilities.

About this text

  • As published by Municode, retrieved 2026-11-23
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

(a) Timing of installation. Construction of the stormwater system shall be initiated as part of the grading of the site. Stormwater detention facilities shall be constructed prior to the installation of any other site improvements, and may be utilized under proper design as sedimentation basins during development. Installation of all other storm drainage pipes, culverts, headwalls, and ditches, shall be coordinated with the construction of streets and other site improvements, as appropriate.

(b) Maintenance responsibilities.

(1) It shall be the responsibility of the developer to maintain all facilities required by the stormwater management plan during construction and for a 1.5-year maintenance period following approval of the final subdivision plat or issuance of a certificate of occupancy, as applicable. The developer shall be responsible for periodic removal of silt that may collect during that period and for removing temporary structures or facilities at the completion of the construction.

(2) The owner of the property shall be responsible for maintaining the permanent facilities identified by the stormwater management plan to remain after construction is complete, following the 1.5-year maintenance period.

(3) Should an owner or developer, whichever is the responsible party, fail to maintain the stormwater management facilities in a state of service intended by the stormwater management plan, then the public works department shall notify the responsible party in writing of the deficiencies and specific minimum maintenance requirements to remedy such deficiencies.

(4) If the responsible party fails to perform the required maintenance work within a reasonable period of time (30 days maximum) then the owner shall be in violation of the provisions of this Development Code and subject to enforcement under the provisions of the administration and enforcement article of this Development Code.

History

The history line the source prints at the end of the section.

(Ord. of 10-13-2020)

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:barrow-county/zoning/89-1259@2026-11-23-b95a1d54ba

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Barrow County Zoning Ordinance, Sec. 89-1259. Installation of stormwater drainage facilities | Georgia Commons