Sec. 89-1316. Special use approval.

About this text

  • As posted on the city's website, retrieved 2026-11-11

Certain uses asshown on Tables 2.2 and 2.3 require a special use approval prior to being allowed on a property.

A special use may be approved by the Town Council under the procedures in this section. In addition, the Town Council following the procedures in this section may also approve changes in the conditions of approval pertaining to a specific special use approval.

(a) Initiation ofspecial use request.

(1) The owner of the property affected, or their authorized representative may initiate an application for a special use for any property or properties.

(2) All applications shall be submitted to the Town’s designee on the appropriate application forms. A nonrefundable fee, if any, as set by the Town Council from time to time, shall accompany all applications. Completed forms, plus any information the applicant feels to be pertinent is to be filed with the planning and community development department.

(3) The Town or its designee shall review the application for completeness within five days of submission. Incomplete or improper applications will be returned to the applicant.

(4) An application for a special use affecting the same property shall not be considered by the Town Council more often than once every 12 months from the date of action by the Town Council denying the special use; provided, however, that the Town Council may approve a reduction in the waiting period to no less than six months. In any event, the council may consider an application for a special use within the 12-month time period in connection with settlement of litigation or pursuant to an order by a court of competent jurisdiction without complying with any of the procedural formalities set forth herein, and subject only to the requirements of the Georgia Zoning Procedures Law, O.C.G.A. § 36-66-1 et seq.

(b) Special use concept plan.

(1) An application for a special use shall be accompanied by a concept plan if any new construction is proposed or alteration of the site is required under the site or development design standards of this Development Code.

(2) A concept plan may be prepared by the applicant, a professional engineer, a registered land surveyor, a landscape architect, a land planner or any other person familiar with land development activities.

(3) The concept plan shall be drawn to approximate scale on a boundary survey of the tract or on a property map showing the approximate location of the boundaries and dimensions of the tract.

(4) The concept plan shall show the following:

a. A location sketch of the property in relation to the surrounding area with regard to wellknown landmarks such as arterial streets or railroads. Sketches may be drawn in freehand and at a scale sufficient to show clearly the information required, but not less than one inch equal to 2,000 feet. US. Geological Survey maps may be used as a reference guide for the location concept.

b. Zoning district classification of the subject property and all adjacent properties, and zoning district boundaries if they cross the property. The number of acres of land in each zoning classification on the property (or square feet if less than one acre).

c. Man-made features within and adjacent to the property, including existing streets and names, city and county political boundary lines, and other significant information such as location of bridges, utility lines, existing buildings to remain, and other features as appropriate to the nature of the request.

d. Natural features, such as the 100-year floodplain, and protected wetlands and stream buffers required under the buffers and tree conservation article of this Development Code.

e. A statement as to the proposed use of the property and the amount of development proposed, such as the number of acres of land in the property (orsquare feet if less than one acre), the number of dwelling units or the gross nonresidential floor area, and the number of parking spaces.

f. The proposed project layout including the approximate outline and location of all buildings, and the location of all minimum building setback lines, outdoor storage areas, buffers, parking areas and driveways.

g. A statement as to the source of domestic water supply

h. A statement as to the provision for sanitary sewage disposal.

i. The approximate location of proposed stormwater detention facilities.

j. The approximate location of proposed access to the public road system.

(5) The concept plan shall also indicate:

a. Name and address of the property owner.

b. Name, address, and telephone number of the applicant (if different than the owner).

c. If drawn on a boundary survey: date of survey and source of datum.

d. Date of plan drawing, and revision dates, as appropriate.

e. North point and approximate scale of the drawing.

f. Location (tax map and parcel number) and size of the property in acres (or in square feet if less than an acre).

g. Such additional information as may be useful to permit an understanding of the proposed use and development of the property.

(c) Impact analysis.

(1) If the special use request has been initiated by an owner or their representative, the application must be accompanied by a written, documented analysis of the proposed use with regard to each of the standards for special use approval enumerated under subsection (e).

(2) A special use application for a proposed development that is capable of generating 1,000 average daily vehicle trips or more shall be accompanied by a traffic study, prepared by a professional engineer registered in Georgia, under guidelines available from the public works department.

Anticipated vehicle trips may be based upon the latest edition of "Trip Generation" published by the Institute of Transportation Engineers. The Town’s designee may waive this requirement when conditions warrant.

(3) A traffic study, prepared by a professional engineer registered in Georgia, shall also be required for a proposed modification to a previously approved special use if the average daily vehicle trips will increase by 10 percent or more than calculated for the original special use approval, or average daily vehicle trips will exceed 1,000 for the first time. The Town’s designee may waive this requirement when conditions warrant.

(4) For a proposed development that will generate fewer than 1,000 average daily vehicle trips or an increase of less than ten percent, a traffic study, prepared by a professional engineer registered in Georgia, may be required by the public works director. Determination of such requirements will be made within five working days of receipt of the application for the special use and must be submitted to the Town Council at least five working days prior to the first public hearing.

(5) A traffic study or other studies of the impact of the proposed development may be required by the Town Council as deemed necessary for adequate consideration and a fully-informed decision on the rezoning request, relative to the standards for special use consideration contained in subsection (e), below.

(d) Process for special use approval. Before the Town Council may take final action on a proposed special use, the Town Council shall each hold a public hearing on the proposal pursuant to the notice and hearing requirements of the Georgia Zoning Procedures Act.

(1) Public notice.

a. At least 15 days prior to the Council’s public hearing but not more than 45 days prior to the Town Council's public hearing, notice shall be published in a newspaper of general circulation within the county. The notice shall state the time, place and purpose of the hearing.

b. A special use request initiated by an owner or their representative shall be heard at a public hearing only upon:

1. The published notice, in addition to the requirements above, shall include the location of the property, the present zoning classification of the property, and the proposed zoning classification of the property requested; and

2. At least 15 days prior to the public hearing, the applicantshall post a sign orsigns, as provided by the planning and community development department, stating the date, time and place for the scheduled Town Council public hearing, the present zoning classification and the nature of the proposed zoning change. One such sign shall be placed in a conspicuous location along each street frontage of the property for which the rezoning has been requested. If the property has no street frontage, the sign shall be placed on each street from which access will be gained to the property.

(2) Public hearings; procedures. The public hearing held by the Town Council for a special use is to be conducted in the following manner:

a. The Mayor, who will act as the presiding official, will convene the public hearing at the scheduled time and place.

b. The presiding official will call for each proposed special use to be presented.

c. No person in attendance is to speak unless first formally recognized by the presiding official.

Upon rising to speak each person recognized shall state his or her name and home address.

1. The presiding official may place reasonable limits on the number of persons who may speak for or against a proposal, on the time allowed for each speaker, and on the total time allowed for presentation of the proposed special use.

2. No less than ten minutes will be provided for all of those speaking in support of a special use approval and no less than ten minutes shall be provided for all of those speaking against, unlesssuch proponents or opponents take lesstime than the minimum allowed.

3. If reasonable time limitations permit, any member of the general public may speak at a hearing.

d. The applicant will be allowed to speak first in order to present the application. Others in support of the application may then speak, followed by those in opposition to the application. The applicant will then be allowed time for rebuttal. Rebuttal must be limited to points or issues raised by opponents to the application at the hearing.

e. Following the presentation of positions by members of the public, a recommendation from the Town’s designee shall be presented.

f. During the public hearing, the members of the Town Council may ask questions at any time.

Time devoted to questions and answers will not be counted against any time limitations that have been imposed on presentations.

(3) Decision.

a. The Town Council shall consider the special use application at the next meeting scheduled for the purpose of considering special use applications for which adequate notice has or can be published.

b. In considering a special use request, action shall be taken by the Town Council by vote of the members present, as follows:

1. A motion to approve or deny an application must be approved by an affirmative vote of at least a majority of a quorum of the members present in order for the motion to be approved.

2. If a motion to approve an application fails, the application is automatically denied. If a motion to deny an application fails, another motion would be in order.

3. If a vote results in a tie among the council members, the Mayor shall cast his or her vote to break the tie. In the absence of the chair, a tie vote shall automatically table the matter until the next regular zoning meeting of the Town Council.

4. If no action is taken on an application, it shall be considered tabled and action deferred to the next regular zoning meeting of the Town Council.

5. A final decision must be made no later than the third meeting at which the rezoning application appears on the board's agenda (i.e., following the council’s public hearing, the application may not be deferred or tabled more than twice).

If, at the third meeting, the council is unable to take final action, the application shall be considered denied.

c. In taking action on an application, the Town Council may:

1. Approve, approve with conditions, or deny the proposal; or

2. Allow withdrawal if so requested by the applicant (with or without imposing a 12-month period during which another special use on the property may not be considered); or

3. Table the proposal for consideration at its next scheduled meeting; or

4. Return the proposal to the planning commission for further consideration.

(e) Standards forspecial use consideration.

(1) Approval of special use. A use that would be allowed otherwise permitted within a zoning district with special use approval shall be considered to be compatible with other uses permitted in the district, provided that due consideration is given to the following objective criteria. Emphasis may be placed on those criteria most applicable to the specific use proposed:

a. Will the proposed special use be consistent with the stated purpose of the zoning district in which it will be located?

b. Is the proposed special use compatible with the goals, objectives, purpose and intent of the comprehensive plan?

c. Will the establishment of the special use impede the normal and orderly development of surrounding property for uses predominate in the area?

d. Is the location and character of the proposed special use consistent with a desirable pattern of development for the locality in general?

e. Is or will the type of street providing access to the use be adequate to serve the proposed special use?

f. Is or will accessinto and out of the property be adequate to provide for traffic and pedestrian safety, the anticipated volume of traffic flow, and access by emergency vehicles?

g. Are or will public facilities such as schools, water or sewer utilities, and police or fire protection be adequate to serve the special use?

h. Are or will refuse, service, parking and loading areas on the property be located or screened to protect other properties in the area from such adverse effects as noise, light, glare or odor?

i. Will the hours and manner of operation of the special use have no adverse effects on other properties in the area?

j. Will the height, size or location of the buildings or other structures on the property be compatible with the height, size or location of buildings or other structures on neighboring properties?

(2) Change in conditions of special use approval. Any application that proposes a change in the conditions of approval previously established by the Town Council through action on a special use shall be reviewed in light of the standards set forth in this section for a special use, as appropriate.

(f) Withdrawal of special use request. Any applicant wishing to withdraw a special use application prior to final action by the Town Council shall file a written request for withdrawal with the planning and community development director.

(1) If the request for withdrawal is received prior to the publication of notice for the public hearing, the application shall be withdrawn administratively by the planning and community development director without restriction on the refiling of a proposed special use on the property in the future.

(2) Should any request for withdrawal be made by the applicant after the planning commission hearing but before the Town Council' hearing, the application shall remain on the Town Council' public hearing agenda and the withdrawal request shall be considered for approval or denial, with or without prejudice, by the Town Council.

(g) Effect of special use denial.

(1) If an application for special use approval is denied by the Town Council, then any portion of the same property may not again be considered for approval of the same or another special use for a period of 12 months from the date of the denial action by the Town Council.

(2) The Town Council may only reconsider property for special use approval within the 12-month time period in connection with settlement of litigation or pursuant to an order by a court of competent jurisdiction. However, the council, if time permits, shall direct staff to advertise, post the property, and notify the applicant and owner in writing prior to taking such action.

(h) Effect of special use approval.

(1) Approval of a special use shall be in full force and effect upon approval by the Town Council.

(2) A special use approval.

(3) For a property on which a use, building, structure or other improvements existed in conformity with this Development Code prior to the effective date of a special use approval affecting the property, any such use, building, structure or other improvements no longer in conformance shall be governed under the provisions of article I of this Development Code relating to grandfathered development.

(4) Construction of any use, building, structure, or other improvements for which a building permit has been issued in conformity with this Development Code prior to the effective date of a special use approval affecting the property may continue to completion in accordance with the provisions for exemptions of previously issued permits in article I and, upon completion, shall be governed under the provisions of the grandfathered development section of said article, as applicable.

(i) Vesting of special use approval. After an approval has been granted by the Town Council for a special use, the applicant, agent or property owner has 24 months to vest the special use approval. To vest a special use approval and forego its expiration, the applicant must record a final subdivision plat, receive project approval of a preliminary plat or site plan, obtain a building permit or lawfully initiate the use, whichever occurs first. If the applicant, agent, or property owner fails to vest the special use approval, the Town Council may initiate a special use application to revert the property to the previously zoned condition. Such reversionary action shall proceed in accordance with provisions of this article pertaining to special use approvals. The owner of the property will be notified of the reversionary action and afforded an opportunity to appear before the Town Council to show just cause why the reversionary action should not be taken.

Read this code where it is posted (city website) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:bethlehem/zoning/89-1316@2026-11-11-d24cbd8b4d