Bishop · Zoning Ordinance
Article XV - ADMINISTRATION, ENF ORCEMENT, PENALTIES AND REMEDIES
Section 1502. Construction Progress.
About this text
- As posted on the city's website, retrieved 2026-11-14
- Read by OCR from a scanned page: a character, a name, or a number may be misread.
Any Building Permit issued shall become invalid unless the work authorized by the permit shall have been commenced within six (6) months of the date of issue or if the work authorized by the permit is suspended or abandoned for a period of one (1) year.
Read this code where it is posted (city website (Google Drive link)) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.