12.6. Conditional Use Permit.

About this text

  • As posted on the city's website, retrieved 2026-11-14

A building permit for a conditional use shall not be approved until such conditional use has been approved by the Planning Commission and payment of the conditional use permit fee as set forth in the then current City of Blythe Fee Schedule has been made.

12. 7 Certificate of Occupancy. A Certificate of Occupancy issued by the Building Inspector shall be required in advance of any occupancy or use of the following:

I. Any building hereafter erected or enlarged

2. Any change in use of an existing building to a different use

3. Any vacant land except for the raising of crops

4. Any change in non-conforming use No certificate of occupancy shall be issued unless the lot or building or structure complies with all the provisions of this Ordinance. A record of all Certificates of Occupancy shall be kept on file in the City Office and a copy shall be furnished on request to any person having a proprietary or tenancy interest in the building or land involved. If the Certificate of Occupancy is not granted upon request, the Building Inspector and/or City Clerk shall state in writing the reason the certificate was not granted.

Read this code where it is posted (city website) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:blythe/zoning/12.6@2026-11-14-f5162b66f3

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Blythe Zoning Ordinance, 12.6. Conditional Use Permit | Georgia Commons