Bogart · Zoning Ordinance
Article 10 - Project Design and Construction Standards / Division I - PROJECT DESIGN / 1017 - Location of utilities and street cuts.
Sec. 1017.02. Pavement cuts.
About this text
- As posted on the city's website, retrieved 2026-11-14
a. If utility services are installed after the streets have been paved (i.e., under existing streets), such utility services shall be installed by boring under the street. Note that this applies only to services and not the distribution system in the development. See Sec. 1008.05.h(11).
b. When it is necessary for a subdivider or any utility company to break existing base or pavement for the installation of services, or any other purpose, the subdivider or utility company shall be financially responsible for the repair of the pavement. The pavement shall be repaired with a patch in accordance with standards developed by the City Engineer/ Public Works Director, and in accordance with all other specifications required herein for construction of streets.
(1) No existing City road can be open cut unless unusual circumstances warrant it. All utility construction plans within City right-of-way shall be reviewed and approved by the City Engineer/ Public Works Director.
(2) If a pavement cut is approved, all trenches shall be backfilled and compacted the same day the trench is opened. Trenches under the paving shall be returned to 95 percent compaction. The backfill in all such ditches will be thoroughly compacted in 6-inch lifts, the subgrade shall be brought to the lines, grades, and typical roadway section required by City specifications. See also Sec. 1020 regarding excavating and trenching requirements.