Article 12 - Procedures and Permits / Division II - PROJECT APPROVAL / 1216 - Major subdivisions and other development projects.
Sec. 1216.02. Preliminary plat or site plan; approval procedure.
About this text
- As posted on the city's website, retrieved 2026-11-14
a. The subdivider/developer shall have a registered Landscape Architect, Engineer, or Surveyor prepare a preliminary plat or preliminary site plan.
b. The subdivider/developer shall submit the preliminary plat or preliminary site plan to the Planning Department in accordance with the schedule published by the Planning Department, but in no case less than 15 days prior to the next regular meeting of the Development Review Committee.
c. The Planning Director shall have 5 work days from the submission of the application to review the application for completeness. Incomplete applications will not be accepted for processing and will be returned to the applicant, who shall have 3 work days in which to resubmit the application complete in all respects.
d. The Planning Department shall notify the Development Review Committee of the submission of a complete application and make copies available for members of the Committee for their review.
e. For subdivisions abutting a State highway:
(1) If a proposed subdivision includes or abuts on any part of the State Highway System, two copies of the proposed subdivision plat shall be forwarded by the Planning Department to the appropriate office of the Georgia Department of Transportation for recommendation and approval as provided in O.C.G.A.
32-6-151.
(2) In the event the Department of Transportation recommends rejection or it fails to act within 30 days from submission, then the deadline for approval or disapproval of the plat by the Planning Department shall be no earlier than 5 working days after receipt of the Department's action or the expiration of the 30 days without action, whichever is later.
f. The preliminary plat or preliminary site plan shall be approved, disapproved, or approved with modification within 60 days after the plat or site plan has been submitted complete in all details and as required under this Development Code. If action is not taken within the said stated time, then the plat or site plan shall be considered approved and certified as approved on demand. However, the subdivider/developer may waive this requirement.
Approval of a preliminary plat or site plan shall not constitute approval of the final plat, site development or construction plans. Rather it shall be deemed an expression of approval to the general layout submitted on the preliminary plat or site plan as a guide Sec. 1216 Major subdivisions and other development projects.
to the preparation of the construction plans and final plat which will be submitted for City approval and recorded upon fulfillment of the requirements of this Development Code.