Article 12 - Procedures and Permits / Division III - DEVELOPMENT CONSTRUCTION APPROVAL

Sec. 1220.04. Process for approval of development permit.

About this text

  • As posted on the city's website, retrieved 2026-11-14

An application for a development permit may proceed simultaneously with an application for project approval of a preliminary subdivision plat or site plan, but may not be issued prior to approval of such plat or plan by the Planning Department.

a. The application for a development permit shall be submitted to the Planning Department and must include the following:

(1) Application on the form furnished by the Planning Department, requesting review for issuance of a development permit.

(2) Copies in the number required by the Planning Director of:

(a) The preliminary plat or preliminary site plan requesting or reflecting project approval by the Planning Director.

(b) The construction plans prepared in conformance with the specifications and standards in this Development Code under Sec. 1221, below.

(3) Two copies of the hydrology study.

(4) Payment of any development permit fee, as established from time to time by the Mayor and Council.

b. The application will be checked for completeness within 5 work days of its submission.

Incomplete applications will be returned to the applicant, who shall have 3 work days in which to resubmit the application complete in all respects.

c. Upon acceptance of a development permit application, the Planning Director shall:

(1) Refer the soil erosion and sedimentation control plan to the Soil & Water Conservation District for their review and approval or disapproval concerning the adequacy of the erosion and sedimentation control plan. No development permit will be issued unless the plan has been approved by the District and the Planning Department, and any variances and bonding, if required, have been obtained.

(2) Refer the grading plan, the stormwater management plan, the floodplain management/flood damage prevention plan (if any), and the street improvements plan to the City Engineer/ Public Works Department for its review and approval or disapproval. No development permit will be issued unless the plans have been approved by the City Engineer/ Public Works Department.

(3) Refer the water and sewerage public utility plans to the Water Resources Department for its review and approval or disapproval.

(4) Refer the on-site septic system plans to the County Health Department for its review and approval or disapproval.

Read this code where it is posted (city website) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:bogart/zoning/1220.04@2026-11-14-adcc09303d

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Bogart Zoning Ordinance, Sec. 1220.04. Process for approval of development permit | Georgia Commons