The Planning Director is responsible for administering and enforcing the building codes of the City.

a. Building permit application.

Application for a building permit shall be made to the Planning Department in a number of copies as established by the Planning Director. The application shall include:

(a) Application on the form furnished by the Code Enforcement Director, requesting issuance of a building permit.

(b) A copy of the preliminary site plan approved by the Planning Director if a multi-family or nonresidential development.

(c) All applications for building permits shall be accompanied by a drawing, showing the actual dimensions of the lot to be built upon, and the size and location on the lot or structure to be erected, moved, added to or structurally altered. For single-family and two-family residences, such plans shall be prepared on an 8½ x 11-inch sheet size.

(d) The application shall include such other information as lawfully may be required by the Planning Director, including:

i. Existing or proposed building or alteration;

ii. Existing or proposed uses of the building and land;

iii. The number dwelling units the building is designed to accommodate for residential buildings, or the floor area (in square feet) of nonresidential buildings;

iv. Conditions existing on the lot; and

v. Such other matters as may be necessary to determine conformance with, and provide for the enforcement of this Code or conditions of zoning approval.

(e) Architectural building plans for principal multi-family or non-residential buildings in a number of copies as established by the Planning Director. Such plans shall be prepared in conformance with this Development Code and the applicable building codes. Such plans shall be prepared by or under the supervision of an architect registered in Georgia, who shall sign and seal each sheet in the original set of drawings.

(f) County Health Department approval if an on-site sewage disposal system has been allowed

(g) Payment of the building permit application and review fee as may be established by the Mayor and Council from time to time.

(h) Water meter receipt and sanitary sewage receipt, when applicable, issued by the Water Resources Department.

b. Review procedures.

(1) The application will be checked by the Planning Director for completeness within 10 work days. Incomplete applications will be returned to the applicant.

(2) Within 2 weeks following receipt of a complete application for residential, or 4 weeks for nonresidential, the Planning Director shall indicate on the building plans approval or disapproval and attest to same by his signature. One copy shall be returned to the applicant and the original copy shall be retained by the Planning Director.

Read this code where it is posted (city website) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:bogart/zoning/1225.03@2026-11-14-bbc9643f81

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Bogart Zoning Ordinance, Sec. 1225.03. Procedures to obtain a building permit | Georgia Commons