a. A stream buffer is to be included within a conservation or natural resources easement that meets the requirements of this Article. b. No land disturbing activities shall be conducted within a stream buffer and a stream buffer shall remain in its natural, undisturbed state of vegetation until all land disturbing activities on the construction site are completed. Land disturbing activities may only be allowed as follows: (1) Where the EPD Director determines to allow a variance that is at least as protective of natural resources and the environment; or (2) Where otherwise allowed by the EPD Director pursuant to O.C.G.A. 12-2-8; or (3) Where a drainage structure or a roadway structure must be constructed, provided that adequate erosion control measures are incorporated in the project plans and specifications and are implemented; provided, however, that stream buffers established pursuant to part 6 of article 5, chapter 5 of title 12, of the Official Code of Georgia, the Georgia Water Quality Control Act, shall remain in force unless a variance is granted by the EPD Director. c. Once the final stabilization of the site is achieved, a stream buffer may be thinned or trimmed of vegetation, consistent with the terms of any applicable conservation or natural resources easement, as long as a protective vegetative cover remains to protect water quality and aquatic habitat and a natural canopy is left in sufficient quantity to keep shade on the stream bed. d. Any person constructing a single family residence, when such residence is constructed by or under contract with the owner for his or her own occupancy, may thin or trim vegetation in a stream buffer at any time, consistent with the terms of any applicable conservation or natural resources easement, as long as protective vegetative cover remains to protect water quality and aquatic habitat and a natural canopy is left in sufficient quantity to keep shade on the stream bed.