3.4. Site Plan Requirements

About this text

  • As posted on the city's website, retrieved 2026-11-11

A. Prior to the issuance of a Development Permit, a site plan must be approved for any new use or change of use and for all construction including expansions and additions.

Exemption of the requirement for a site plan for a change of use may be granted by the Planning Director where the development

complies with all of the following:

1. No new square footage is proposed to be constructed for the new use.

2. The proposed use is a permitted use in the applicable district.

3. The proposed use is a similar or less intensive use than the last authorized use of the property.

4. Thresholds for water use, septic systems, etc. are similar or less intensive than the last authorized use of the property.

5. The site complies with the minimum parking requirements for the proposed use and all other existing uses on site.

6. The site complied with all conditions of approval, and site/landscape standards in effect at the time the previous use was

authorized.

B. Exemption from the site plan approval process for a change of use does not also exempt the development from all other

necessary permits and inspections.

C. A site plan must be submitted in accordance with the requirements set for below. The site plan is considered to be filed when it has been accepted by the Planning Director as meeting the requirements of this section.

D. The Planning Director may request printed copies of the site plan to distribute to the Town Engineer, Public Utilities Director, or others for review. The applicant is responsible for delivering site plans to all applicable county, state, and federal entities for

approval. Evidence of approval by these agencies must be presented to the Planning Director prior to the issuance of a

development permit.

E. A site plan must be prepared by an Engineer or Architect who is registered by the State and must include, in addition to the certified property lines, all applicable information as required on the site plan review checklist, a copy of which is available at the Planning and Development Department office.

F. Site plan review and inspection fees as established by the Town will be collected prior to the issuance of a Development Permit and Building Permit.

G. The following required plans must be submitted at the time of site plan submittal and prior to the issuance of a development permit unless the Planning Director

determines than any of these are not necessary:

1. Site plan.

2. Landscape plan.

3. Erosion and sedimentation control plan.

4. Grading plan.

5. Stormwater management plan.

6. Water and sewer plan if required.

7. Any other information deemed necessary by the Planning Director, Town Engineer, or Public Utilities Director to be included on the plan.

8. Road right-of-way, driveway, and access design.

H. Upon approval of the site plan by all the required departments, the Planning Director may issue the Development Permit.

I. Any deviations from an approved site plan must be shown on a revised site plan and approved by the Town employee(s) having

jurisdiction over the change. The Fire Marshal must approve all construction plans and

submit to the building official written verification of approval and compliance with applicable fire codes.

Read this code where it is posted (city website (Revize)) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:braselton/zoning/3.4@2026-11-11-9e0b7dffab

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Braselton Zoning Ordinance, 3.4. Site Plan Requirements | Georgia Commons