A. Upon approval of a preliminary plat, site plan and development plans, the Planning Director and Town Engineer may issue a Development Permit authorizing development activities to begin based on the approved documents. A development permit is an official authorization permitting clearing, grubbing, grading, and/or construction of storm drainage facilities, utilities, access drives, streets, parking, and other improvements exclusive of buildings. A permit authorizing clearing, grubbing, and grading may be issued by the Planning Director prior to the issuance of a development permit based on approval of a grading plan, soil erosion and sedimentation control plan, and hydrology study by the applicable Soil and Water Conservation District. B. Development permits for subdivisions expire if the development activity described in the permit is not begun within 12 months of the date of issuance. Renewal of the permit after expiration must be in accordance with the requirements of this Development Code. C. Model home construction may be allowed prior to final plat approval after a building permit is obtained with the following requirements: 1. Access to the home(s) must be adequate to accommodate the general public and emergency service vehicles. 2. All storm water, roads, and improvements have been installed and inspected. 3. Addresses have been issued by the appropriate agency/county. 4. A final certificate of occupancy may not be issued until final plat is approved and recorded. D. Prior to the issuance of a development permit for any construction other than a single-family residential structure, a review and approval of all development and construction plans must take place. No clearing, grubbing, or grading may be undertaken until a permit has been approved. E. The Planning Director must issue a Development Permit before the Building Official issues any type of building permit. F. If the applicant does not begin any site development activities within 12 months of the date of issuance of the development permit, then the development permit is null and void. However, the development permit may be reissued under the development requirements in place at the time that the original permit was approved.