A. Street Types All new streets must be designed in accordance with one of the street types in this section except where alternate designs (including the use of one-way streets) are authorized by approval of both the Town Engineer and the Planning Director.

B. Private Street Standards

1. All new streets must be public streets or private streets built to the standards of this Development Code.

2. Private streets (except alleys) must be located on a separate parcel owned by the property owners association for the development. Private streets may not be located on easements. An access easement must be recorded with each lot's deed to grant the right of access to every lot served by the street, as well as the right to place public and private utilities in the street parcel.

3. Easements for alleys must have the same width as the required right-of-way width for public alleys.

4. The Town will not maintain roadways, signs, or drainage improvements on private streets. The property owners association must provide all maintenance activities as well as related actions to ensure compliance with Town’s NPDES permit for stormwater discharges.

5. Any gate across a private street that limits access must provide unimpeded access by emergency vehicles, governmental vehicles on official business, and delivery services including the U.S. Postal Service.

Accessibility to gated communities must comply with all standards and requirements of the County Fire Chief for access activation.

C. Streetscape Improvements

1. Where a new development abuts an existing street, the streetscape requirements of this article must be met along the side of the street abutting the development.

2. For those properties for which inadequate right-of-way exists to install the improvements specified in this article, additional right-of-way may be dedicated to the applicable jurisdiction in order for the improvements to be installed. If such rightof-way is donated, the required parking lot setback may be reduced by an amount

equal to additional right-of-way donated. In no case may the parking lot setback be less than 5 feet.

3. Where streetscape improvements are installed on private property, appropriate easements must be provided to ensure adequate access. Any such easement agreements must be approved by the Town Manager.

D. Developments Abutting Existing Narrow Streets Where a proposed development abuts an existing street that is narrower than would be required by this section, the developer must dedicate additional right-of-way to meet onehalf of the minimum right-of-way requirement for the applicable street type, as measured

from the center of the existing right-of-way or the center of the existing street, whichever is greater. The Town Engineer may also require additional right-of-way to be dedicated for any turn lanes, deceleration lanes, and acceleration lanes required by the Town or

GDOT.

E. Medians Medians may be added to any street section and will result in an increased right-of-way width. Vertical or high back six-inch concrete curb are required around all medians.

Medians must be either designed to slope toward the outside curb of a street or provide gutters and an adequate drainage system within the median.

F. Landscape Strip All required landscape strips must be planted with a combination of shrubs, perennials, groundcovers, and grass, as approved by the Planning Director. Where parallel parking spaces are provided along non-residential streets, the adjacent landscape strip must be paved for at least 18 inches (measured from the face of curb) and provide intermittent strips of pavement at least 24 inches wide to allow pedestrian access to the sidewalk.

G. Local Residential Street (No Parking)

H. Local Residential Street (Parallel Parking) Parallel parking may be provided on one or both sides, but must be provided on all block faces with townhouses.

I. Residential Alley

J. Commercial Street/Residential Boulevard The required boulevard width and type is based on projected average daily traffic count (ADT) as follows.

The applicant must provide a traffic study to forecast the projected average daily traffic count (ADT) based on the reallocation of existing traffic from adjacent streets as well as the expected traffic generation of the proposed development and any other new developments along the new street.

Pavement and right-of-way widths must match those in the proposed sections that follow. Medians are encouraged. Parallel parking is required on all boulevard sections except those that immediately abut single-family detached dwellings.

1. Where the projected average daily traffic count is between 2,500 and 15,000, a 2-lane boulevard is required, with or without a median, and with or without parallel parking.

2. Where the projected average daily traffic count is more than 15,000, a 4-lane boulevard is required, with or without a median, and with or without parallel parking.

K. Multi-Use Trail Multi-use trails may be provided in dedicated rights-of-way or easements independent of streets. Where trails meet a street, a 5-foot flare must be provided, with a ramp to the street and bollards spaced 7 feet apart to block motorized traffic except golf carts. For new developments that abut any state route, the required 6-foot sidewalk provided adjacent to the development must be constructed as a 10-foot wide multi-use trail.

Read this code where it is posted (city website (Revize)) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:braselton/zoning/9.3@2026-11-11-a2d95f227d

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Braselton Zoning Ordinance, 9.3. Street Design Requirements | Georgia Commons