Sec. 104-45. Design standards for sanitary sewer.
About this text
- As published by Municode, current through 2025-10-13
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
(a) Pipe.
(1) Lateral lines extending from the city sanitary sewer system shall be a minimum of eight inches, located ten feet off of the curb opposite the waterline. Services shall be a minimum of six inches. Minimum cover shall be four feet with PVC pipe. Minimum grade shall be such that the line will maintain a minimum of two ft./sec. velocity.
(2) The pipe shall be polyvinyl chloride, PVC, ASTM D-3034 DR-35, or mechanical joint ductile iron. The D.I. pipe shall conform to ANSI spec A21.51 (AWWA C151) class 50 wall thickness. The D.I. pipe shall be cement-lined inside and bituminous coated outside as per ANSI spec A21.4 (AWWA C151). The inside lining shall have 40 mils nominal thickness of polybond lining.
(b) Manholes.
(1) Materials. Manhole risers shall be pre-cast as per ASTM C478, four-foot inside diameter, five-inch wall thickness, plastic steps with three-eighth-inch rebar. The riser tongue and groove joint shall be scaled with butyl rubber, bitumastic material or O-ring gasket conforming to ASTM C 443. The frame and cover shall be cast iron, 370# standard, watertight, or vented, as required. The lid shall have "SEWER" cast in raised letters.
(2) Installation. Precast concrete manholes shall be bedded on not less than six inches of compacted crushed stone. The crushed stone shall extend not less than six inches outside the walls of the manhole, and shall be compacted under entire length of pipe within manhole excavation. A maximum of three brick courses will be allowed for adjustment of the manhole frame and cover to be flush with the proposed grade.
(3) Pipe connection to manhole. Connections of pipe to manhole for four-inch through 15-inch pipe shall be made with a flexible joint system. The joint system shall be a neoprene or synthetic rubber boot or sleeve, either cast or core drilled into the wall of manhole. The boot or sleeve shall be clamped and seated to the pipe with a stainless steel band. Manhole inverts shall be carefully constructed with cement grout, Class "B" concrete, or cement mortar brickwork; special care shall be taken to lay the channel and adjacent pipes to grade. Channels shall be properly formed, rounded, and troweled smooth. The connections of the sewer with the wall and channel of the manhole shall be tight and smooth.
(4) Drop manholes. Drop pipe shall not be smaller than eight inches. Generally, drop pipe shall be one size smaller than the sewer which they serve. Openings in walls of precast concrete manholes for drop connections shall not be made at joints. Drop connection fittings and riser pipe shall be encased in brick and mortar or formed Class "C" concrete.
(c) Service lines. At the time the main sewer is laid, the developer shall provide a six-inch PVC service line for all lots. The pipe shall be polyvinyl chloride, PVC, ASTM D-3034 DR-35.
Service lines shall extend from the main sewer to the property line or edge of easement.
(1) Service branch connection for PVC pipe. Service branch connection for PVC pipe shall consist of molded or fabricated "T-Y" (in-line) branch fitting with all gasketed connections. Taps will be permitted only by special permission of the engineer and shall be a gasketed fitting in conjunction with a repair sleeve coupling or a gasketed saddle tee with all stainless steel clamps. Saddles may be mounted on pipe with solvent cement or gasket but shall be secured by metal banding. Saddles shall be installed in accordance with manufacturer's recommendations. Holes for saddle connections shall be made by mechanical hole cutters or by keyhole saw or saber saw. Holes to tee saddles shall be laid out with a template and shall be deburred and carefully beveled where required to provide a smooth hole shaped to conform to the fitting. Fittings which are prefabricated using pipe sections, molded saddles and PVC solvent cement may be used, provided the solvent cement used in fabrication has cured at least 24 hours prior to installation. Cemented mitered connections without socket reinforcement shall not be used. PVC primer and solvent cement shall be used in accordance with the manufacturer's current recommendations and ASTM D 2855, as amended to date. After solvent cementing saddles, temporary band clamps must be quickly placed both upstream and downstream of the saddle and tightened.
(2) Service branches.
a. In general, service branches shall incline upward at approximately 45 degrees above a horizontal line normal to the direction of flow. Service lines shall be laid on a straight line and grade from the sewer or riser to the property line, and in no event shall service lines be less than 3½ feet deep to invert of the pipe at the property line.
b. Where required, short radius bends shall be used to connect the service branch to the house service line. Pipe service branches, together with bends, shall be placed on a compacted bed of crushed stone in such a manner as to be self-supporting and to relieve the strain on branches and bends.
(3) Risers. Where trench depths are such that risers are required for clay pipe, service lines shall be installed by excavating into ditch bank and installing riser in a vertical position against undisturbed earth, and the entire length of the pipe containing the riser encased in concrete in conformance with the details shown on the drawings. Risers shall extend to the heights directed by the design engineer and shall be encased in a brick masonry stack. No concrete encasement will be required for PVC riser. Bends shall be used to connect the riser to the house service lines.
(4) Stoppers, caps and plugs. All service connections shall be closed with factory manufactured pipe stopper of such design and secured in such a manner as to not leak under a maximum hydrostatic head of ten feet or five psi air pressure. The pipe stopper shall be able to be removed without special tools, excessive force or breakage of the pipe bell.
(5) Marking tape. Detectable marking tape shall be installed at the end of all service lines.
The tape shall be two inches in width imprinted with the words "BURIED SEWER".
The tape shall extend from the invert of the service line to the ground surface and shall be firmly secured at the invert, but shall not be tied to house services lines.
(d) Construction.
(1) Bedding of PVC, and ductile iron pipe. Bedding for PVC pipe shall be in accordance with ASTM D 2321. The pipe shall be bedded in compacted crushed stone bedding placed on a flat trench bottom. The compacted crushed stone bedding shall have a minimum thickness of six inches under the barrel and shall extend to the springline of the pipe.
Bell holes shall be provided so as to relieve pipe bells of all load, but small enough to assure that support is provided throughout the length of the pipe barrel. Crushed stone bedding material shall conform to the latest revision of ASTM C 33, gradation #67 (ASTM #67), varying in sizes one-fourth-inch through three-fourths-inch.
(2) PVC pipe backfill. Backfill above the springline with Class I, II, or III material shall then be carried to a point six inches above the top of pipe, using hand tools for tamping.
Silt, clays, including inorganic clays and silts of medium to high plasticity and liquid limits will not be allowed in a wet ditch. If the remaining backfill material contains large particles which could damage the pipe from impact during placement the initial backfill shall be increased to 12 inches above the top of the pipe. Puddling will not be allowed as a method of compaction. The remaining backfill shall be as specified in subsections (d)(5) and (6) of this section. Pipe shall have at least 30 inches of cover before wheel loading and at least 48 inches of cover before using heavy-duty tamping equipment such as a hydrohammer.
(3) Definition of bedding material. Class I, II, and III materials are defined as follows:
Class I Angular ¼ to ¾ inches graded stone.
Class II Coarse sands and gravels having a maximum particle size of ¾ inches with a small percentages of fines.
Class III Fine sand and clayey (clay filled) gravels, including fine sands, sand-clay mixtures and gravel-clay mixtures.
(4) Ductile iron pipe.
a. The pipe shall be installed on a flat bottom trench on undisturbed earth with excavation for bells. Lightly consolidated backfill to centerline of pipe, additional backfill shall be as specified in subsections (d)(5) and (6) of this section.
b. Maximum depth of cover for ductile iron pipe for the various classes and sizes to be installed should be as recommended by the pipe manufacturer.
c. Ductile iron, mechanical or push-on joint, pipe may be used on piers in gravity sewer lines. Pipe shall be laid with One-fourth-inch clearance in each joint to provide for expansion. On mechanical joint pipe the bolts shall be tightened alternately 180 degrees apart but be left "finger-tight" until the sewage is diverted into the sewers; then bolts shall be further tightened a sufficient amount which will prevent leakage of the joint, but which will not prevent slippage which may occur because of temperature stresses.
(5) Selected backfilling. All trenches shall be backfilled immediately after pipes are laid therein, and joints have been inspected by the engineer, unless other protection of the pipeline is directed. Selected backfill material shall consist of finely divided earth, stone dust, sand, crushed stone, or other approved material carefully placed about the pipe and up to a height of at least 12 inches above the top of the pipe barrel, and in uniform layers not exceeding six inches in thickness, each layer thoroughly compacted with proper hand tools in a manner which will not disturb and/or injure the pipe. Backfilling shall be carried on simultaneously on both sides of the pipe and in a manner which will prevent injurious side pressures. If suitable select materials are not available from the trench excavation, the contractor will be required to obtain the select materials elsewhere.
(6) General backfilling. After selected backfill material has been placed and tamped, the remainder of the trench may be backfilled with general excavated material, except that no rock, unless in small shattered fragments, will be permitted to be mixed with other backfill material.
(7) Pipe stabilization. Wherever the subgrade is by nature too soft or mucky for the proper installation of the pipe, the contractor shall undercut the trench and backfill with crusher run stone or crushed stone three-fourths-inch in size and less. The stone shall be brought to the subgrade required by the class of bedding for the particular location and compacted.
(8) Jointing dissimilar pipe. Dissimilar pipes shall be joined together using flexible couplings. Concrete collars will be permitted only if flexible couplings are not available in sizes needed. Concrete collar shall be constructed of Class "A" concrete and shall be poured so as to completely and securely encase the entire joint.
(9) Connections to existing sewers. At locations where new sewers are shown to be connected to existing sewers at a new manhole, the contractor shall first expose the existing sewer, install a supporting timber beam, strap the pipe with suitable straps, and attach the straps to the beam; all in a manner which will bridge the excavation for the new manhole. The manhole shall then be constructed, and be complete with invert, frame, and cover. Under special conditions, and with approval by the engineer, the contractor may temporarily block and/or divert sewage flows to facilitate construction operations.
Actual physical connection of the sewers will be made at a later date, as directed by the engineer.
(10) Replacement of concrete curb and gutter, street, driveway and sidewalk. Concrete curb and gutter, street, driveway and sidewalk shall be replaced with Class "A," 3,000 psi concrete of the same thickness and dimensions as was removed.
(11) Roadway and railroad crossing. The subdivider or his contractor shall install pipe lines across a roadway or railroad in accordance with the applicable regulations of the state department of transportation or governing railroad body. Recently paved city streets shall be bored and cased in steel casing at least 1½ times the proposed pipe outside diameter. Steel pipe casing shall be manufactured from steel conforming to ASTM A 252 Grade 2 with a minimum yield strength of 35,000 psi before cold forming. The casing ten inches in diameter and less shall be a minimum of 0.375-inch wall thickness.
Casing greater than ten inches shall be a minimum of one-half-inch wall thickness.
When crossing city streets, the casing shall extend at least five feet off of the edge of pavement on each side. Coating for the casing is not required. The pipe shall be supported by skids within the casing such that the pipe bell does not rest on the bottom of the casing. When the city street is in disrepair, the street may be open cut trench in accordance with state department of transportation standard 1401.
(e) Testing and cleaning. Before acceptance of any sewer or systems of sewers, lines shall be cleaned and tested. Where any obstruction is met, the contractor will be required to clean the sewers by means of rods, swabs, or other instruments. Lines and manholes shall be clean before final inspection. Pipe lines shall be straight and show a uniform grade between manholes. The contractor shall be required to correct any defective pipe which may be disclosed during the inspection. Each section of sewer between manholes shall show, upon examination from either end, a reasonably full circle of light.
(f) Deflection testing for PVC pipe. The maximum deflection in the installed PVC pipeline shall not exceed five percent of the pipe's original internal diameter. Deflection testing will be required using either a deflectometer or a "GO-NO-GO" mandrel. Where deflection is found to be in excess of five percent of the original pipe diameter, the contractor shall excavate to the point of excess deflection and carefully compact around the point where excess deflection was found. The line shall then be retested for deflection. However, should after the initial testing the deflection pipe fail to return to the original size (inside diameter), the line shall be replaced.
(g) Leakage tests. All sewer lines, including house service lines, shall be tested for leakage, in the presence of the engineer or his representative, before being placed into service. Tests shall be conducted by one or a combination of the following three methods:
(1) Infiltration test. Where natural groundwater levels stand a minimum of two feet above the top of the pipe, the amount of leakage may be determined from measurements made at the lower end of the sewer section under test. Sewers above the test section shall be closed before testing by the installation of suitable watertight bulkheads. The length of the test section shall be determined by the engineer. The average of six readings at five-minute intervals will be used to determine the rate of infiltration for any one test section. The rate of infiltration of groundwater into any test section of sewer, including manholes, shall not exceed the following:
Sewer Size (in.) Gallons Per 24 Hrs. Per Foot of Sewer 6 0.12 8 0.15 10 0.19 12 0.22 15 0.28
(2) Exfiltration test. Where natural groundwater levels do not stand two feet above the top of the pipe, an exfiltration test shall be conducted on each section of sewer. The test shall be performed up to an average maximum hydrostatic head of ten feet. The test shall be conducted in the following manner:
a. The ends of the pipe in the test section shall be closed with suitable watertight bulkheads. Inserted into each bulkhead at the top of the sewer pipe shall be a two-inch pipe nipple with an elbow. At the upper end of the test section a riser pipe shall be installed. The test section of pipe shall be filled through the pipe connection in the lower bulkhead which shall be fitted with a tight valve, until all air is exhausted and until water overflows the riser pipe at the upper end. Water may be introduced into the pipe 24 hours prior to the test period to allow complete saturation. House service lines, if installed, shall also be fitted with suitable bulkheads having provisions for the release of air while the test section is being filled with water.
b. During the test period, which shall extend over a period of 30 minutes, water shall be introduced into the riser pipe from measured containers at such intervals as are necessary to maintain the water level at the top of the riser pipe. The total volume of water added during the 30-minute test period shall not exceed that shown for infiltration in subsection (g)(1) of this section.
(3) Low-pressure air test. Where sewer grades are such that preclude performance of the exfiltration test or at the contractor's option, a low-pressure air test shall be conducted on each section of sewer after completion and before acceptance.
a. Prior to air testing, the section of sewer between manholes shall be thoroughly cleaned and wetted. Immediately after cleaning or while the pipe is water soaked, the sewer shall be tested with low-pressure air. At the contractor's option sewers may be tested in lengths between manholes or in short sections (25 feet or less) using air-lock balls pulled through the line from manhole to manhole. Air shall be slowly supplied to the plugged sewer section until internal air pressure reaches approximately 4.0 psi. After this pressure is reached and the pressure allowed to stabilize (approximately two to five minutes), the pressure may be reduced to 3.5 psi before starting the tests. If a 1.0 psi drop does not occur within the test time, then the line has passed the test. If the pressure drops more than 1.0 psi during the test time, the line is presumed to have failed the test, and the contractor will be required to locate the failure, make necessary repairs and retest the line. Minimum test time for various pipe sizes, in accordance with ASTM C 828, as amended to date, is as follows:
Nominal Pipe Size (in.) Time (min.)/100 4 0.3 6 0.7 8 1.2 10 1.5 12 1.8
b. Required test equipment includes air-lock balls, braces, air hose, air source, timer, rotometer as applicable, cut-off valves, pressure reducing valve, 0-15 pressure gauge, 0-5 pressure gauge with gradations in 0.1 psi and accuracy of two percent.
c. The contractor shall keep records of all tests made. A copy of such records will be given to the engineer or the owner. Such records shall show date, line number and stations, operator and such other pertinent information as required by the engineer.
(4) Repairs. All visible leaks shall be repaired regardless of whether infiltration, exfiltration or air test is within allowable limits. No sewer will be accepted until leakage tests demonstrate compliance with one of the above leakage test methods.
History
(Code 1996, § 82-172; Ord. of 3-8-1999, pt. V, art. 2)