Sec. 23-26-42. Cases where data are not available.

About this text

  • As published by Municode, retrieved 2026-11-11
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

In the event that information submitted by the applicant of the discretionary development proposal is sufficient to calculate the trip generation that would be expected to result from the proposed development, but trip generation rates or other data are not available or in sufficient quantity of studies to make a determination of applicability under the terms of this chapter, this section shall apply.

(1) The director shall first consult with the city engineer to determine if:

a. Professionally acceptable trip generation rates applicable to the subject development exist from other reputable sources, such as the Journal of the Institute of Transportation Engineers;

b. Other trip generation studies of similar developments are available; or

c. Professionally acceptable trip generation rates for one or more similar land uses can be used in making the determination of applicability.

If the city engineer is able to provide such information and determines it is professionally reputable, then the director shall use said data as may be interpreted by the city engineer to make the determination of applicability. The director and city engineer shall have no more than ten working days to comply with the provisions of this section, when it applies.

(2) In the event the director is unable to make a determination of applicability after consulting with the city engineer pursuant to this section, the director shall notify the proposed applicant in writing that professionally accepted trip generation rates are not available for purposes of making a determination of applicability.

(3) Upon receipt of notice described in this section, the applicant for a discretionary development proposal shall have 30 days to have a qualified professional prepare and submit a peak-hour trip generation study as defined by this chapter.

History

The history line the source prints at the end of the section.

(Ord. No. 1081, 9-20-2023)

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:brunswick/zoning/23-26-42@2026-11-11-638631c238

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Brunswick Zoning Ordinance, Sec. 23-26-42. Cases where data are not available | Georgia Commons