All detention and or retention facilities plans shall be at a scale of not less than one-inch equals 50 feet with a maximum contour interval of two feet. The plans shall be based on a stage-storage design and shall meet the following requirements: (1) Maximum storage requirements for the proposed facility shall be based on the storage volume required for the 50-year frequency storm event, and the 100-year storm event must be routed through the facility without overtopping the embankment, by use of an emergency spillway or other structure. (2) The stage-storage design increment shall not exceed one-foot in elevation. (3) The outlet device shall be designed to limit post-developed runoff rates to less than or equal to the pre-developed rates for the two-, five-, ten-, 25-, and 50-year frequency storms. (4) The type and size of pipes to be used for the outlet along with detail drawings and specifications for all facilities shall be shown. (5) Actual results obtained from routing the two-, five-, ten-, 25-, 50-, and 100-year post-developed storm hydrographs through the facility shall be included. (6) A summary chart showing maximum facility elevations, maximum water surface elevations, storage required, and pre-developed and post-developed discharge rates for the two-, five-, ten-, 25-, 50- and 100-year frequency storms shall be included. (7) Stormwater detention/retention facilities shall be graded so as to provide positive drainage. The minimum slope along the bottom of the facility shall be two percent. Side slopes shall not be steeper than three feet horizontal to one-foot vertical.