A. General. 1) After civil/site documents are approved by the DRT, a developer or his authorized agent must apply for a land disturbance permit (LDP) prior to beginning any development activities. 2) The development inspectors are charged with issuance of any LDPs and ensuring compliance with regulations through all phases of the permit. 3) The City of Canton issues the following types of land disturbance permits: a. Timbering. b. Clearing and grubbing. c. Clearing and grading. d. Full site LDP. 4) Work shall not be done beyond the point indicated in each successive inspection without first obtaining the approval of the development inspector. The development inspector shall make the required inspections and shall either indicate the portion of the work that is satisfactory as completed, or notify the permit holder or his or her agent wherein the same fails to comply with this UDC. Any portions that do not comply shall be corrected before work continues on that portion. 5) All permits shall be posted in a visible place so that they will be legible from the frontage roadway. 6) Additional permits may be required for activities outside of the LDP process such as burning or blasting. 7) Land disturbance permits expire after six months of no visible sign of progress. The city engineer can approve One six-month extension if requested prior to the original expiration date. B. Application and payment of fees. 1) The following items shall be completed prior to applying for a land disturbance permit: a. Apply for NPDES permit to the state and the city at least 14 days prior to beginning construction. b. Applicant must bring the certificate of mailing and a copy of the NPDES check sent to the state. 2) Once the application has been submitted and the fees have been paid, the applicant will request a pre-construction meeting. C. Pre-construction meeting. 1) The developer is responsible for requesting a pre-construction meeting once the LDP application has been submitted and fees paid. 2) The developer shall bring the approved set of civil/site documents to the pre-construction meeting. D. Pre-construction inspection. 1) The developer is responsible for requesting a pre-construction inspection once the following items are completed: a. Advance warning signs posted with speed reduction advisory plates placed on connecting thoroughfares at 1,000 feet and 500 feet points on either side of the intersection. b. All buffers (state, city and those required by zoning) protected with orange tree save fencing material reviewed and approved by the development inspector. c. Construction exit installed and permit board posted. 2) If the items listed under subsection D.1 above are not approved by the development inspector, the developer will have to complete the insufficient items, call for another inspection and pay a re-inspection fee in accordance with the fee schedule adopted by the Canton City Council. 3) At the development inspector's discretion, the pre-construction meeting and inspection may be combined based on the scope of the project and level of experience of the developer. 4) LDP card will be issued by the development inspector. E. Phase I: Clearing. 1) The clearing phase of the project is when the developer clears the site of trees and vegetation according to the approved civil/site documents. The developer is also responsible during this phase for installing and maintaining required erosion and sedimentation control devices. 2) During the clearing phase, only 50 acres may be disturbed at one time. 3) The developer is responsible for completing the following items, if applicable, prior to the clearing inspection: a. All trees and other vegetation removed, mulched or burned. b. All Phase I erosion control measures installed. c. All sediment ponds installed, matted and grassed. d. Seven-day letter from the design engineer concerning all erosion control devices. F. Phase II and III: Grading. 1) The grading phase of the project is when the developer reshapes the contours of the property, constructs public infrastructure elements and installs landscaping as shown on the approved civil/site documents. During this phase, the development inspector will be conducting on-going erosion control, stormwater and transportation inspections based on the pace of construction of the project. 2) Erosion control inspections ensure the following items are installed and maintained as required: a. Active grassing every seven days on non-active disturbed areas. b. Silt fence. c. Check dams. d. Temporary ponds. e. Permanent ponds. 3) Transportation inspections ensure the following items are installed according to the approved civil/site documents and City of Canton Specifications: a. Curb and gutter. b. Subgrade. c. Base. d. Asphalt. e. Entrances—Sight distance and water flows. 4) Stormwater inspections ensure the following items are installed according to the approved civil/site documents and City of Canton Specifications: a. Pipes. b. Catch basins, inverts, grout, tops, BMP's, etc. G. Final site approval. 1) The final site inspections ensure that all site improvements are complete and the project is ready to move into the maintenance period prior to city acceptance. These inspections will review the following: a. As-builts. b. Storm drains. c. Permanent grass. d. Silt fence removal. e. Water flow (easements/drainage and entrances). f. Pond inspection/letter/water quality. g. Street signs. h. Striping. i. Landscaping (reviewed by the zoning administrator). j. Retaining wall letters. 2) The final site inspections shall only occur after the final plat and as-builts have been submitted. 3) Upon the completion of paving, the developer shall request a final punch list in writing from the development inspector. The development inspector shall transmit the completed punch list along with the calculated maintenance guarantee amount. 4) If the development inspector finds upon inspection that all improvements meet the city requirements, the inspector shall provide written "notice of acceptance" to the developer. 5) The developer shall post the maintenance guarantee before the final plat is recorded (see also section 108.04.02). 6) If the development inspector finds, upon inspection, that the improvements do not meet the city requirements, the inspector shall provide the developer with written notice detailing the reasons for rejection of the improvements. 7) The development inspector shall re-inspect the project for compliance and release when requested by the developer. If any further re-inspection is necessary, then a re-inspection fee shall be levied in accordance with the fee schedule that is adopted by the Canton City Council. All re-inspection fees shall be paid in full prior to the approval of a final plat (residential) or certificate of occupancy (non-residential). 8) Once the final plat has been approved and all required public improvements complete except work covered by a performance guarantee (see section 108.04.03), the final plat shall be signed by the responsible city departments and presented by the developer to the Clerk of the Superior Court of Cherokee County for recording.