Canton · Zoning Ordinance

Part III - DEVELOPMENT CODE / Chapter 110 - DESIGN STANDARDS: WATER SYSTEM TABLE OF CONTENTS

110.02.01. Pre-construction requirements.

About this text

  • As published by Municode, retrieved 2026-11-11
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

A. Water pressure flow test.

1) A water pressure test must be run on the existing water line to determine the adequacy of water supply line for the project.

2) The test shall consist of a fire hydrant flow test and a 24-hour pressure test.

3) Test information shall consist of the following:

a. Static pressure and elevation of static gauge.

b. Recorded flow in GPM and residual pressure.

c. Maximum elevation in development.

d. Available flow at maximum elevation with 20 PSI residual pressure.

e. Twenty-four hour pressure chart.

4) An adequate supply of water for the proposed project must be available prior to the approval of any plans. Flow tests are valid for one year.

5) The fire department will run the test at the developer's expense.

6) All projects which have flow test results with static pressure less than 35 psi will require a special design study to be accomplished and submitted to the city for approval to ensure no problems are encountered during peak demands. This study must be approved by the city prior to construction plan approval.

7) Plans shall not be stamped or approved until the flow test is completed.

B. Plan review process.

1) Preliminary plan requirements.

a. Preliminary plans shall include the portion of the county tax maps highlighting the land to be developed, the type of development, the number of units, the tie-in location and the general plan for water supply. The plans shall also include the name, address and telephone number of the developer or his representative.

i. Questions relating to adequate fire protection, multiple feeds, water supply and proposed location of connection(s) should be resolved at this stage before proceeding with detailed planning.

ii. The submittal for preliminary review must include all land to be developed although the land is to be developed in several phases or units.

iii. Adequacy determinations of the existing water supply system will be made for the entire project.

b. Developer/land owner must submit a set of preliminary plans for any proposed project to the City of Canton Engineering Department prior to submitting the construction plans.

2) Construction plan requirements.

a. The developer must then submit six paper copies of construction plans, plus the electronic data on disc, as outlined in these specifications, to the City of Canton Engineering Department for review.

b. All plans for water main projects shall bear a suitable title showing the name of the project.

c. Plans shall show the scale in feet, the north arrow, date, the name of the design professional, the design professional's signature and his registration stamp. All design professionals preparing construction plans and specifications must be registered in the State of Georgia as a professional engineer or a registered land surveyor.

d. If the project requires a water line extension of more than 500 feet to reach the project, a registered professional engineer must design and stamp the line extension.

e. The cover sheet shall include the owner's/developer's name, address, telephone number, and fax number, plus the design professional's name, address, telephone number, and fax number. The cover sheet shall also include the funding source if state or federally funded, and a detailed project location map. The cover sheet shall also show the numbers of the tax map and parcel in bold letters.

f. The plans shall be clear and legible. They shall be drawn to a scale which will permit all necessary information to be plainly shown.

g. Plans shall be submitted on 22-inch by 34-inch drawing sheets and shall be submitted concurrently in an "Autocad" drawing electronic format. A sheet index shall be provided, as well as a legend of symbols used.

h. Horizontal locations shall be referenced to Georgia State Plane Coordinates (west zone feet). Vertical locations shall be shown referenced to mean sea level. Reference all horizontal locations to the NAD83/94 (latest adjustment) datum and reference all vertical locations to the NAVD88 datum. All orthometric locations shall be referenced to Geoid 99/03. All points are subject to verification by the City of Canton Engineering Department.

i. Water line locations shall be shown on plans and submitted in ASCII Text or EXCEL electronic format for each point. The developer shall provide ASCII or EXCEL spread sheet files for coordinate data (comma delimited). Each point I.D. (valves, water main, etc.) shall be shown at the correct location on the printed plans.

j. Water Mains along city, county or state roads and cross country shall be located at 50-foot intervals (ground and top of pipe). If water main is within the development and maintains a constant distance behind curb and constant depth, locate at all transitions (vertical and horizontal).

k. All fittings, tees and bends, valves, and air release valves shall also be located. All vertical locations shall be finished ground and top of pipe. The contractor shall place a vertical piece of two-inch diameter PVC pipe on top of the pipe at all bends, tees, fittings, valves, elevation transitions, horizontal transitions and every 50 feet along the length of the water main (city, county or state roads and cross country) for the purpose of enabling the surveyor/engineer to locate the water main for "as-builts." The contractor will then be responsible for removing the vertical PVC sections after the as-built locations have been verified by the city. The ground, top of pipe, top of fitting and top of valve elevation of shall be located. The size and material of all pipes, valves and fittings shall be recorded.

l. All electronic point data shall include:

i. Point ID (see city staff).

ii. Northing.

iii. Easting.

iv. Ground elevation.

v. Top of pipe, valve or hydrant elevation.

vi. Point description (pipe, fitting or valve type and size).

m. Construction plans shall consist of the following:

i. Site plan showing the water layout only with project name, streets, street names, topography with contour lines at two-foot intervals, location map, lot layout (if subdivision) or building location (multi-family, commercial or industrial site), land lots, district and north arrow. Lot numbers shall run in consecutive order and there shall be no duplicate lot numbers within the project. Note if any other utilities are existing. Plan scale shall be a minimum of one inch equals 100 feet.

Both the construction plans and "as-builts" ("as-built" plans document the final location of infrastructure and utilities) shall show station numbers along the alignment plus call out the specific stations of all features such as tees, crosses, fire hydrants, bends, etc. along with the point I.D. match lines shall be provided where necessary.

ii. Proposed pipe materials, sizes, lengths and alignment.

iii. Proposed service lateral locations.

iv. Location, type and size of water valves and air release valves (to be installed at highest points of system).

v. Thrust blocks where used.

vi. Fire hydrant locations.

vii. Water system materials.

viii. Location and sizes of existing water lines surrounding project, with nearest line valve in each direction from proposed connection.

ix. Detail of connection to existing water lines.

x. Proposed meter sizes and locations.

xi. Detailed plan of fire line meters, detector meters, compound meters, backflow preventers, etc. if applicable.

xii. Any other items incidental to the proposed system.

xiii. Details of special water line installations such as stream crossings, elevated lines on piers, bridges, pipe bedding, special highway crossings, railroad crossings, etc.

xiv. Show all right-of-way widths, easement widths and pavement widths.

xv. Plan and profile sheets shall be prepared with a horizontal scale of one inch equals 50 feet and a vertical scale of one inch equals ten feet. These scales also apply to any profile view of sanitary sewers.

xvi. Bench marks and control points shall be shown on the plan sheets. Horizontal and vertical coordinate data shall be provided for each bench mark and control point. The vertical datum used shall be the elevation above mean sea level.

xvii. A sheet index shall be provided, as well as a legend of symbols used.

xviii. Each plan sheet should include a note stating the contractor must call the utilities protection center "call before you dig" telephone number (1-800-282-7411) four days before starting any excavation.

xix. All construction plans submitted for review of revisions requested by the city must list each revised item with a cloud around the revised area on the plan sheet and must identify which reviewing authority requested the revision.

xx. Each set of construction plans shall include a reproduction of standard detail W725 "call before you dig" detail (see chapter 112 of UDC) from the utilities protection center.

n. The general notes for water system construction shown in standard Detail W726 shall be included in each set of plans. See chapter 112 of this UDC.

C. Plan approval. Work shall not begin until plan approval is received from the City of Canton.

The city engineer shall have final approval of the preliminary plans, construction plans and final plans. If a discrepancy occurs between the approved plans and this UDC, this UDC shall be the superseding document. The city engineer may modify or cause to be modified any plans that he believes are in the best interest and future integrity of the City of Canton.

D. Revisions to approved plans.

1) When any deviations from approved plans are proposed, the city engineer shall be notified for authorization. Revised plans should be submitted as soon as possible to the city engineer. Minor changes not affecting water system operation may be allowed in the field during construction by the city engineer. The city engineer shall have authority as to what constitutes a minor or major change. "As-built" drawings and the required electronic data on disc shall be furnished to the City of Canton Engineering Department at the completion of construction.

2) Any section or unit must be built in accordance with the plans. If the developer decides to phase a section off, a new set of plans showing the phase change will have to be resubmitted and approved.

E. Approval by other government agencies. No part of the plan approval process is intended to relieve the developer of the responsibility to comply with the minimum applicable standards of any appropriate local, state or federal regulatory agency.

F. Relocation of existing water and sewer facilities. All existing water or sewer facilities that have to be relocated, as might occur at roadway entrances, easements, elevation changes, etc., will be relocated by the developer's contractor at the developer's expense. The city will inspect all such work prior to acceptance.

G. Easement acquisition and utility encroachment permits.

1) It shall be the responsibility of the developer to obtain any off-site easements required to connect the project to the existing water system. Easements will be conveyed to the City of Canton for all facilities which are to be conveyed to the city. This process must be started early enough to allow construction of the water mains before any building construction is to begin. No building permits, water meter or sewer tap applications shall be issued until off-site water mains and sewers have been constructed and accepted. This condition shall override any provision for speed up of house starts such as furnishing a bond to guarantee completion of the streets and other appurtenances.

2) Easement drawings shall be prepared for work outside the development prior to approval of the water system plans. The drawings shall be of a size suitable for legal recording and shall be prepared by a registered land surveyor. The drawing must be clear and legible for printing. The drawing shall be at a reasonable scale and shall not be a reduced copy of the plan sheet. The drawing will show property lines, the name of property owners with the length of line encroaching on each property owner, size of line, width of permanent and construction easement, scale of drawing, north arrow, land lot and district numbers, and a tie to the nearest land lot corner. Any streets or other existing easements shall also be shown.

Easement agreements referencing these drawings shall be prepared and attached to the drawings, signed by the property owners, and recorded at the Cherokee County Clerk of Superior Court's office. A copy of the recorded easement agreement shall be provided to the city before the construction plans are approved and stamped.

3) All easements shall allow adequate room to construct the water main and appurtenances.

Permanent easements shall be a minimum of 20 feet wide. Wider easements shall be required where water lines are deeper than normal. The maximum cross-slope of the permanent easement shall be ten percent.

History

The history line the source prints at the end of the section.

(Ord. No. 2014-18, § 2, 8-21-2014; Ord. No. 2022-0317-01, 3-17-2022)

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:canton/zoning/110.02.01@2026-11-11-c73e9867c1

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Canton Zoning Ordinance, 110.02.01. Pre-construction requirements | Georgia Commons