A. Request for inspection. The applicant for a building sewer connection permit shall notify the City of Canton Building Department when the building sewer is ready for inspection and connection to the city wastewater system. The connection and testing shall be made in the presence of the building inspector or his representative. B. Guarding excavations. All excavations for building sewer installation shall be adequately guarded with barricades and lights in compliance with all OSHA and Georgia Department of Transportation requirements so as to protect the public from hazard. Streets, sidewalks, parkways and other public property disturbed in the course of the work shall be restored to a good as new condition in a manner satisfactory to the city. C. Restoration of disturbed public property. 1) A three-day notice is required. 2) All water or wastewater construction work conducted on the public right-of-way or any public property shall be conducted only with proper permission from the City of Canton Engineering Department. The developer shall be required to post a bond with the city so that proper restoration of the disturbed are is assured. All disturbed areas as a result of such construction shall be restored to a condition that is "as good as new." The scheduling of such construction activities shall be as approved by the city manager if such scheduling approval is determined to be in the public's best interest. D. Backflow prevention. 1) When required. All wastewater treatment plants, and water plants, commercial businesses, industries, or institutions shall be required to install backflow prevention mechanisms. Additionally, approved backflow preventers or vacuum breakers shall be installed with all plumbing fixtures or equipment for which the potable water supply outlet may be submerged without the protection of a minimum air gap. The particular backflow prevention devices utilized in any given situation shall be as specified in the plumbing code or as approved by the city. 2) Minimum required air gap. The minimum required air gap shall be measured vertically from the lowest end of a potable water outlet to the flood rim or line of the fixture or receptacle into which it discharges. The minimum required air gap shall be twice the effective opening of a potable water outlet unless the outlet is a distance less than three times the effective opening away form a wall or similar vertical surface in which cases the minimum required air gap shall be three times the effective opening of the outlet. In no case shall the minimum required air gap be less than is provided in the plumbing code. E. Temporary water supply standpipes in elbows only. 1) All standpipes installed for the purpose of providing temporary water supply at any given location shall be installed on a 90-degree elbow. 2) Tees, crosses and wyes or other connecting device shall not be utilized. 3) When the permanent water connection is made, the temporary elbow shall be removed. F. Capping and sealing of discontinued water and sewer connections. All water and sewer connections for which service has been discontinued as a result of the demolition of the structure being served by the connection, or for any other reasons, shall be properly and permanently capped and sealed to prevent the entrance of ground or surface water in the case of sewers and the escape of potable water in the case of water lines. G. Location of water meters. 1) All water meters shall in installed at an easily accessible location on or near the property line of the premises being served adjacent to the public right-of-way. Water meters shall not be installed behind enclosed fences, in pave driveways, in paved parking areas or sidewalks. 2) Generally, the city shall locate meters at or near the customer's curb or property line. When it is impractical to locate meters at or near the customer's curb or property line, the city may locate a meter in any other reasonable convenient or accessible place which affords protection against damage. 3) When meters are grouped, the city shall tag each meter to identify the customer whose services are measured by that meter. H. Wastewater lift stations. 1) All wastewater lift stations installed in the city which serve two or more buildings shall be designed and constructed in strict conformity to the wastewater lift station specifications sections of chapter 111 of this UDC. 2) Engineering plans shall be prepared for all wastewater lift stations and such plans shall be approved by the city water system prior to construction.