A. Connection to live sewers.
1) Any single-family or multi-family dwelling, commercial or industrial establishment shall be connected to public sewer when sewerage lines are available for connection.
2) Connection shall be at the cost of the property owner.
B. Availability shall be defined as follows:
1) Sewerage shall be considered available to an existing single-family dwelling when the dwelling can be connected by gravity flow to a line in any public right-of-way or easement that passes the property at any point.
2) Sewerage shall be considered available to any new single-family dwelling when the dwelling can be connected by the installation of 200 linear feet of gravity flow line from the nearest point of the property.
3) Sewerage shall be considered available to any new subdivision when trunk sewers have been extended into the drainage basin. Sewerage shall also be considered available when trunk sewers are constructed under a current funding program. Trunk sewers are those sewers recognized in the facilities plan, or other planning documents of the city. When trunk sewers are to be funded under future bond programs, sewerage will not be considered available.
C. To determine the availability of sewerage to any multi-family dwelling, commercial or industrial tract the sewage effluent for the development will be converted to its equivalent number of single-family dwellings. For comparison purposes, a single-family dwelling generates an effluent of 400 gallons per day of sewage.
D. Dry sewerage systems.
1) In cases where the city is to expend bond funds within a drainage basin in two years but said sewers are not available at present, the developer will be required to install dry lines to serve any structure to be built in the development. These lines will collect at a single point at the property line at the lowest point on the property or at a point designated by the Engineer. The installation of dry lines does not in any way relieve the requirements of the Cherokee County Health Department for approving septic tanks in the development.
2) No dry sewers shall be used until such time as trunk sewers are constructed to an acceptable treatment facility.
3) No pumping and hauling of sewage is allowed.
4) Septic tanks placed on the lots shall be located at a point to facilitate future connection of the home to the tap provided.
E. Sewerage not available.
1) Connection to a public sanitary sewer system is required in each zoning district unless noted in chapter 112 of this UDC.
2) If sewerage is not available nor shall be available in a zoning district that does not require a connection to a public sewer system, a 20-foot permanent and 60-foot construction sanitary sewer easement shall be shown on the plans and dedicated to the City of Canton for future use, in those areas where a proposed subdivision is adjacent to a creek or branch whose drainage area is 200 acres or greater. The City of Canton may at its option require additional easements.
3) Minimum easement widths to be dedicated are 20 feet for permanent easements and 60 feet for construction easements, with the construction easement centered on the permanent easement. Also, in the event that a trunk or interceptor greater than 15 inches is expected to pass through the development, the construction easement width shall be increased to the amount required for construction of the expected sewer.
a. All easements are to be checked in the field and must be adequate for the purpose they are dedicated. Also, consideration must be given for expected building locations and the easement shall be located for the least possibility of conflict before the sewer may be constructed.
b. No structures shall be built on dedicated easements and the city will not be responsible for the removal of fences that are placed on dedicated easements in the event the sewer is constructed.
Septic tanks in these type developments shall be placed in a location to facilitate tie -on of structure to the sewer.
History
(Ord. No. 2014-18, § 2, 8-21-2014)