A. General.

1) All plans for sewerage works shall bear a suitable title showing the name of the project, the name of the sewer basin, and show the scale in feet, the north arrow, date, the name of the engineer, professional engineer signature, and his registration stamp. All engineers preparing construction plans and specifications must be registered in the State of Georgia as a professional engineer.

2) The plans shall be clear and legible. They shall be drawn to a scale which will permit all necessary information to be plainly shown. The plans shall be submitted on 22-inch by 34-inch or 30-inch by 42-inch drawing sheets and shall be submitted concurrently in a "Cad" drawing format that is compatible with the city's GIS system. The datum used should be the elevation above sea level.

B. Plans of sewers. Plans for sewers shall include a site plan, plan and profile sheets, sections and supplementary views, and design drawings for all special fixtures.

1) Site plans.

a. The site plan shall show land lot lines, district and north arrow, lot layout, and existing and proposed building locations. The site plan shall also show all existing and proposed streets and their names, all streams, water courses, and storm drains, and the discharge points for all drainage structures. The site plan shall show the topography with contour lines at suitable intervals. On the site plans, show the sewer layout with existing and proposed lines, line designations and direction of flow. Also show the size of all lines and the locations of proposed services.

b. The design of cross country sewer lines and force mains shall be based on field run surveys. The site plan for cross country sewer lines and force mains need not show contour intervals, but the profiles shall be based on mean sea level elevation. Site plans for lift stations shell show existing and proposed contours.

c. In the event the subdivision is developed in phases, the final construction plans for sewers may be submitted in phases. However, at the time the first phase is submitted, the engineer will submit one copy of the preliminary layout of the entire seer system. This layout will show all lines required to serve any lots to be developed and any surrounding property that may be served through the property. The site plans for each phase shall contain a location plan showing the relationship of the phase to the total project and surrounding streets and sewer outfalls.

2) Plan and profile sheets.

a. Profiles should have a horizontal scale of not more than 100-foot per inch for cross country lines and 50-foot per inch for congested areas. The vertical scale shall ne be more than 10-foot per inch. The plan view should be drawn to the corresponding horizontal scale. The plan view should normally be shown on the same sheet as the profile. In any case, both plan and profile should have line designations, station numbers, manhole numbers and any other indexing necessary to easily correlate the plan and profile view.

b. Plan and profile sheets shall show the following:

i. Location of streets, sewers, and drainage easements.

ii. Profile of ground surface, the grade of the sewer between each manhole, size and material of pipe, length between manholes, invert of sewer in and out of each manhole, and rim elevation of each manhole. All manholes shall be numbered on the plan and correspondingly numbered on the profile. Station numbers shall be shown for each manhole. The profile of adjacent parallel streambeds and of adjacent lake surfaces, low buildings, and lots shall be shown on the profile.

iii. Locations of all special features such as connections to existing sewers, concrete encasements, collar walls, pipe sections, elevated sewers, piers, special manhole covers such as vented outfall covers or sealed covers, etc.

iv. All known existing structures both above and belowground which might interfere with the proposed construction, particularly water mains, gas mains, storm drains, utility conduits, etc.

C. Detail drawings. Special detail drawings made to scale to clearly show the nature of the design shall be furnished to show the following:

1) All stream crossings and storm drain outlets with elevations of the streambed and of normal and extreme high and low flow water levels.

2) Details of special sewer joints and cross sections.

3) Details of special sewer appurtenances such as manholes, service connections, elevated sewers, piers, pipe bedding special highway crossings, railroad crossing, etc.

D. Plan approved.

1) All plans must be submitted to the engineering department. Approval will be given to the design for construction at that time provided design meets the specifications of the city. Once plans are approved, three approved sets shall be submitted to the engineering department.

2) The City of Canton Utilities Engineer may, if he feels it is in the best interest and future integrity of the city, modify or cause to be modified any plans.

3) If a discrepancy occurs between the approved plans and the City of Canton sewer specifications, the specifications shall be the superseding document.

E. Revisions to approved plans.

1) When any deviations from approved plans affecting capacity, flow or operation of units are made, the utilities engineer shall be notified for authorization. Revised plans should be submitted as soon as possible to the city manager and/or his designated representative. Minor changes not affecting capacities, flows or operation may be allowed in the field during construction by the city manager and/or his designated representative.

2) The utilities engineer shall have final authority as to what constitutes a minor or major change. "As-built" plans clearly showing changes shall be submitted to the utilities engineer at the completion of the work.

F. As-built drawings.

1) At the completion of the sewer lines and before the inspection, the contractor will furnish three sets of printed "as-built" plans and electronic files of the project.

2) The "as-built" plans shall show all field changes made to the approved plans.

3) In the event "as-built" drawings cannot be made available at the completion of the sewer line, the utilities engineer may authorize the continuation of the construction; however, the final inspection cannot be conducted and the conditional approval letter cannot be written until "as-built" drawings are received.

4) In the event that the designer does not perform the field staking, the contractor must furnish certification from a licensed engineer or surveyor attesting to the accuracy of all elevations, grades, manhole locations, and service locations. This certification and the certification of the engineer/land surveyor preparing the "as-built" drawings must be shown on the drawings.

5) "As-built" drawings shall include a site plan, plan and profile sheets, and any supplementary drawings and shop drawings. Stationing of the sewer gravity and force main alignments, manholes and service laterals shall be required on the "as-built" drawings as well as the construction drawings. The "as-built" drawings shall meet the same requirements as the construction plans for review.

6) "As-built" drawings shall be submitted on 24-inch by 36-inch or 30-inch by 42-inch drawing sheets and shall be submitted concurrently in a "Cad" drawing electronic format that is compatible with the city's GIS system. The following are specific guidelines for the preparation of the "as-built" drawings:

a. Sewer "as-built" shall be a separate plan.

b. No contour lines.

c. Approximate depth of lateral should be shown.

d. Any lateral that does come out at a 90-degree angle shall show its distance from property pins.

e. Road names shall be on plans.

f. All measurements of laterals should be kept between manholes and both sides shall add up to the distance between manholes.

g. The center of all manhole rims shall be located horizontally and vertically as described above.

h. All lots are to be numbered.

i. Printed "as-builts" are to be clear and legible.

j. Profiles are to be included in all "as-builts."

k. Roads shall be shown on all plans.

l. "As-built" is to be in large clear print on plans.

m. Scale no larger than one inch equals 20 feet, no smaller than one inch equals 100 feet for cross-country lines and one inch equals 50 feet for congested areas.

n. When a phase of a subdivision is completed, a location sketch of the entire subdivision with said phase outlined shall appear on plans.

o. Line designation shall be used for correlation between profiles and plan view.

p. Ground water and solid rock encountered during construction will be noted on "as-builts."

History

The history line the source prints at the end of the section.

(Ord. No. 2014-18, § 2, 8-21-2014)

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:canton/zoning/111.02.04@2026-11-11-8a06833266

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Canton Zoning Ordinance, 111.02.04. Plans | Georgia Commons