Canton · Zoning Ordinance
Part III - DEVELOPMENT CODE / Chapter 111 - DESIGN STANDARDS: SEWER SYSTEM TABLE OF CONTENTS
111.02.06. Materials.
About this text
- As published by Municode, retrieved 2026-11-11
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
A. Ductile iron pipe (DIP).
1) General.
a. Ductile iron sewer pipe shall be required at all utility crossings with less than two feet of clearance, in cross country locations where cover is less than three feet, in streets where cover is less than five feet, in fills, and where PVC sewer pipe has more than 18 feet of cover.
b. Ductile iron pipe shall be designed in accordance with AWWA C-150. The thickness and class of the pipe shall be governed by AWWA C-150.
c. Pipe shall be manufactured in accordance with AWWA C-151 and shall have an outside bitumastic coating per AWWA C151
d. Pipe shall be coal tar epoxy lined and seal coated with approved bituminous seal coat in accordance with AWWA C151, latest revision.
2) Lining material.
a. The interior lining of the pipe and fittings for gravity sewer shall be a ceramic epoxy lining with a minimum thickness of 40 mils.
b. The minimum standard for the lining shall be Induron Protecto 401. The listed product and manufacturer are given to identify the generic type, quality and general composition of the product. similar products may be used but are subject to the approval of the city.
c. Both bare pipe and cement linings conforming to AWWA C104 are NOT allowed for any gravity sanitary sewer pipe.
3) Joints. DIP joints shall be of the bell and spigot type with push-on joints, conforming to AWWAC-111 or mechanical joints.
B. Polyvinyl chloride pipe (PVC).
1) General. The contractor shall provide un-plasticized polyvinyl chloride (PVC) plastic gravity sewer pipe meeting the requirements of ASTM D3034 (latest revision) in the sizes shown unless otherwise indicated on the contract documents.
2) Materials.
a. Pipe and fittings shall meet the requirements as specified under ASTM D3034 (latest revision) for pipe through 15 inches and ASTM F679 for pipe 18 inches through 27 inches.
b. All pipe and fittings shall be suitable for use as a gravity sewer conduit.
c. Bell joints shall consist of an integral wall section with elastomeric gasket joint that provides a watertight seal. Standard laying lengths shall be 20 feet (± one inch).
d. The pipe shall be capable of passing all tests that are detailed in this specification.
e. Minimum wall thickness shall be as shown in table 111-3:
Table 111-3 Minimum Wall Thickness (PVC Pipe) Pipe Diameters, inches Minimum Wall Thickness, inches 4 0.120 6 0.180 8 0.240 10 0.300 12 0.360 15 0.437 18 0.536 21 0.632 24 0.711 27 0.801
3) Fittings.
a. All fittings and accessories shall be manufactured and furnished by the pipe supplier.
b. Fittings shall have bell and/or spigot configurations compatible with that of the pipe and shall have an equivalent wall thickness.
4) Pipe and fittings tests.
a. The contractor will be required to furnish a written outline of the manufacturer's quality control program for the engineer's approval prior to shipping any pipe to the project.
b. Before installing any pipe the contractor shall furnish written certification that all pipe through 15 inches meets ASTM Specification D3034 and for 18 inches through 27 inches must meet ASTM F679.
c. At least one sample from each 100 pieces of pipe furnished shall be subjected to each test outlined under section 8 of ASTM D3034. The samples will be tested by an independent laboratory approved by the city engineer, and a certified copy of results will be furnished to the city engineer.
d. If any test is not met, then nine additional tests of that property will be ordered, and if any of those nine tests are not met, the manufacturer will not be allowed to furnish materials for this project.
e. The cost of all testing shall be included in the contractor's bid proposal and no pipe shall be installed until the testing is complete and approved by the city engineer.
5) Pipe stiffness.
a. Minimum "pipe stiffness" (F/Y) at five percent deflection shall be 46 psi for all sizes, when tested in accordance with ASTM Standard Method of Test D2412 (latest edition), to determine the "External Loading Properties of Plastic Pipe by Parallel Plat Loading."
b. There shall be no evidence of splitting, cracking, or breaking at a deflection of up to 30 percent of the original diameter.
6) Fusion quality. There shall be no evidence of flaking, swelling, or disintegration when the pipe material is tested in accordance with ASTM D2152, "Quality of Extruded Poly (Vinyl Chloride) pipe by Acetone Immersion."
7) Joint tightness.
a. Pipe and fitting joints shall comply withASTM D3212 (latest edition) for "Joints for drain and Sewer Plastic Pipes Using Flexible Elastomeric Seals."
b. Joint assemblies shall not leak when subjected to both an internal and external hydrostatic test at equivalent pressures of 10.8 psi gauge for a period of one hour. Pipes shall be tested in straight alignment, axially deflected position, and by shear load test as otherwise defined in paragraphs 7.2, 7.3, and 7.4 of ASTM D3212.
8) Installation.
a. PVC pipe will be installed in accordance with ASTM D2321 (latest revision).
b. In any area where the pipe is below existing ground water level, the contractor will embed PVC pipe in sand or graded gravel. No special compaction requirements will be necessary; however, the sand or gravel must extend from six inches below the pipe to 12 inches above the pipe, and the material must be firmly placed under the pipe haunches.
c. When embedding PVC pipe in friable, compressible soils (e.g., silt, clay, sandy clay, silty clays, etc.), special care must be exercised to provide a uniform (undisturbed or fully compacted) trench bottom. Additionally, the backfill must be compacted to 95 percent standard proctor in six- to eight-inch lifts to 12 inches above the top of the pipe. Initial backfill shall be compacted to the densities outlined in D2321. The engineer may require up to ten random compaction tests to insure compliance with D2321. If any material tested is less than the required density, the contractor shall re-compact said material at no additional cost to the owner, and the engineer shall then have the right to additional compaction tests at the expense of the contractor to insure compliance with D2321.
d. The contractor shall use SDR-35, for pipe with zero to 20 feet of fill. PVC pipe cannot be used with more than 20 feet of fill.
9) Deflection limit.
a. Vertical deflection of installed pipe shall not exceed seven and one-half percent of the undeflected diameter as defined in table X1.1 of ASTM D3034.
b. Each segment of line (except service lines) will be tested at the end of each month just prior to submitting for payment on that segment. Upon completion of the pipe laying, and at least 30 days after installation (to allow for settling), the pipe will be tested again for final acceptance. The test shall be performed by the contractor pulling a mandrel of specified dimensions through the pipeline.
C. High density polyethylene pipe (HDPE).
1) General.
a. This subsection covers the requirements of high density polyethylene profile wall gravity sewer and drain pipe fittings in nominal sizes 18 inches through 96 inches with integral bell and spigot gasketed and welded joints.
b. HDPE pipe is acceptable only for trenchless technology applications and for small diameter (less than four-inch) force mains. HDPE pipe shall not be specified for open-cut gravity sewers.
2) Classes.
a. Class selection for high density polyethylene profile wall sewer pipe shall be a minimum of class 160 for pipe with zero to 20 feet of fill.
b. Polyethylene pipe cannot be used over 20 feet deep.
3) Material.
a. Pipes and fittings shall be manufactured from high density polyethylene resin compound which shall meet the requirements of type III, class C, category 5, grade P 34 per ASTM D 1248.
Materials meeting the requirements of ASTM D3350 with a cell classification PE 334433C or higher are also suitable. The pipe shall contain a minimum of two percent carbon black as an ultraviolet inhibitor.
4) Pipe dimensions.
a. The average inside diameter and the minimum wall thickness of the waterway of the pipe shall comply with ASTM F894 for RSC class 160 pipe.
5) Joints.
a. The pipe shall be produced with bell and spigot end construction. Joining shall be accomplished by use of neoprene rubber gaskets complying with the physical requirements as specified in
ASTM F477.
b. Joints shall be in accordance with ASTM D3212 and withstand an internal operating pressure of 50 psi.
6) Pipe stiffness.
a. The profile wall shall be substantially strong to protect against any diametrical deformation.
b. All polyethylene profile wall pipe shall have a minimum specific pipe stiffness of 46 psi at a deflection of five percent of the internal diameter when tested and calculated in accordance with ASTM D24212 (latest edition).
7) Retest and rejection.
a. If the results of any tests do not meet the requirements of this specification, the tests may be conducted again in accordance with agreement between purchaser and seller.
b. In retesting, the product requirements of this specification shall be met and the test methods designated in this specification shall be followed. If upon retest failure occurs, the quantity of product represented by the tests shall be rejected.
8) Deflection limit.
a. Vertical deflection of installed pipe shall not exceed seven and one-half percent of the undeflected diameter as defined in table X1.1 of ASTM D3034.
b. Each segment of line (except service lines) will be tested at the end of each month just prior to submitting for payment on that segment. Upon completion of the pipe laying, and at least 30 days after installation (to allow for settling), the pipe will be tested again for final acceptance. The test shall be performed by the contractor pulling a mandrel of specified dimensions through the pipeline.
D. Reinforced concrete pipe (RCP).
1) General. The work included in this subsection includes furnishing all labor, equipment, and materials required to install, test, and inspect reinforced concrete (ASTM C-76) pipe sewers, including all risers, plugs, fittings, and bedding, as shown on the drawings and/or specified herein.
2) Quality assurance.
a. The contractor must submit to the owner and engineer the concrete pipe manufacturer's evidence of a working quality control program for approval, prior to any pipe being manufactured. The program and standards of manufacturing must be established and well defined. The program must include the minimum following requirements:
i. A full-time quality control technician.
ii. A complete and working quality control laboratory capable of testing and recording the requirements set forth in these specifications for concrete pipe.
iii. Written documentation of the concrete pipe manufacturer's performance on a recent sewer project. The performance results must be from a tested and approved installation of the pipe material set forth in this specification from either the owner and/or engineer stating that the pipe tested and met the requirements.
iv. A zero defect program for daily material testing and finished product testing to assure quality control as the pipe is being manufactured and shipped for this particular project.
v. Provide the services of a competent factory representative of the pipe manufacturer for purposes of supervising and/or inspecting the installation of pipe. This service shall be for the duration of the project.
vi. Provide equipment and labor to air test each joint of pipe (30-inch diameter and larger) as it is installed. Joint tester shall be "Cherne Large Diameter Joint Tester" or equal. This testing shall in no way relieve the contractor from the responsibility of performing infiltration/ exfiltration tests.
3) Testing of concrete pipe.
a. Concrete gravity pipe (ASTM C-76) used on this Project shall meet all materials and testing requirements of ASTM C-76, ASTM C-443, and ASTM C-497 (except where modified herein).
Manufacturer shall secure the services of an independent testing laboratory to conduct the tests.
Testing laboratory shall be approved by the Engineer prior to conducting any tests. All testing costs shall be paid for by the pipe manufacturer.
b. Testing shall be in job lots (a job lot is a continuous run of one size of pipe for this project) for a maximum of six percent of pipe quantity or a minimum of five percent of pipe quantity. The test specimen will have a minimum of two joints for pipe of 16-foot laying length. For pipe of 12-foot laying length, the maximum number of joints shall be seven and the minimum number shall be two. Bulkheads will be included in this joint count.
c. A representative of the owner will be present to witness all tests that are conducted at the manufacturer's site and shall record all results. Manufacturer shall notify the engineer at least 48 hours prior to conducting any tests.
d. The following test shall be required:
i. Pipe barrels shall be subjected to an internal hydrostatic pressure of ten psi for ten minutes.
Pipe joints shall be subjected to an internal hydrostatic pressure of 13 psi for ten minutes.
The testing of the joints will be in the straight and deflected alignment.
ii. The manufacturer shall conduct three external load crushing strength tests per job lot. This test shall be by the three-edge bearing method. The test may be taken to ultimate load.
iii. Absorption tests shall be conducted as per ASTM C-497. The absorption rate of the sample from the pipe wall shall not exceed six percent.
e. If any test specimen fails to pass any of the above tests, two additional test specimens shall be chosen at random from the job lot and tested. If either of those two specimens fails the test, then the entire job lot is subject to rejection. If the manufacturer requests further testing, then every section of pipe in the job lot must be tested.
f. In addition to the above tests, manufacturer shall conduct tests to determine alkalinity of cover concrete.
g. Each pipe shall be clearly marked as required by the governing ASTM standard specifications to show its class, date of manufacture, and the name of trademark of the manufacturer.
h. Any pipe or specials which have been broken, cracked or otherwise damaged before or after delivery or which have failed to meet the required tests, shall be removed from the site of the work and shall not be used therein.
4) Guarantee.
a. The contractor shall provide a guarantee against defective materials and workmanship in accordance with the requirements of the section entitled "guarantees and warranties" of these specifications.
5) Material.
a. All concrete pipe and fittings 12 inches in diameter and larger shall be reinforced concrete sewer pipe conforming to the latest requirements of ASTM C-76 with the following modifications:
i. All concrete pipe with zero to 20 feet of fill shall be a minimum of class III with 4,500 psi concrete.
ii. All pipe with 20 to 30 feet of fill shall be class IV with 4,500 psi concrete.
iii. All pipe with 30 feet of fill and over shall be class V with 5,500 psi concrete.
b. Pipe shall have circumferential reinforcement as required for the particular class of pipe furnished. The bell and spigot of the joint shall contain circumferential and longitudinal reinforcement. Reinforced concrete pipe shall be centrifugally cast or vibrated, horizontally or vertically cast or made on a packerhead machine and shall be furnished in lengths not more than 20 feet and not less than eight feet, except where short lengths are required for construction conditions.
Reinforced concrete pipe shall have bell and spigot joints suitable for the use of a rubber gasket to be provided as a part of this item.
c. Concrete pipe for sanitary sewers shall have bell and spigot joints consisting of self-centering steel joint rings securely attached to the pipe reinforcing steel. The steel joint rings shall be suitable for use with a rubber O-ring type gasket to be provided as part of this item.
d. Bell and spigot joints consisting of self-centering steel joint rings shall have the joint rings securely attached to the pipe reinforcing steel. The rings which form the joint shall be made so that they will join with a close, sliding fit. The joint surfaces shall be such that the rubber gasket shall be confined on all sides and shall not support the weight of the pipe.
i. The spigot ring shall have an external groove accurately sized to receive the gasket. Special section steel for spigot rings shall conform to ASTM A-283, grade A, or ASTM A-306, grade 50.
ii. The bell ring shall be flared to permit gradual deformation of the gasket when the joint is assembled. Minimum thickness of bell rings shall be three-sixteenths-inch. Bell rings one-fourth-inch or thicker shall conform to ASTM A-283, grade A, or ASTM A-306, grade 50.
Bells less than one-fourth-inch thick shall conform to ASTM A -570, Grade A.
iii. Each ring shall be precisely sized by expansion beyond the elastic limit of the steel and then gauged on an accurate template. All exposed surfaces of both rings shall be protected by a corrosion-resistant coating of zinc applied by an approved metallizing process after proper cleaning.
6) Lining.
a. The coal tar epoxy system shall be Koppers 300 M, Porter Tarset, Wise Chem CTE 200, Amercoat 78, Protecto 101 or equal.
b. The interior concrete or mortar surfaces of pipe and fittings are to be sandblasted and painted with one coat of a high-build, coal tar epoxy system or two coats of a standard coal tar epoxy system.
The dry film thickness of the total system shall be 16 mils minimum on concrete or mortar surfaces and on steel joint ring surfaces.
c. Sandblasting shall result in a clean dry surface free of oil, grease, or other contaminants. Any air pockets over one-fourth-inch in diameter and one-eighth-inch deep appearing on the concrete surface after sandblasting will be filled with an epoxy sand patching material such as those sold by Sherwin-Williams, Glidden, or Moran. The epoxy sand patch should be troweled prior to the application of the coal tar epoxy.
d. Any steel surfaces to be painted should be sandblasted, solvent cleaned, or wire brushed prior to painting. Application of the coal tar epoxy shall be by brush, roller, or spray system using equipment recommended by the manufacturer of the coal tar epoxy system. The temperature during application and curing of coal tar epoxy shall be as recommended by the manufacturer of the coal tar epoxy. Time between coats (if applicable) shall be as recommended by the manufacturer of the coal tar epoxy.
e. If the inside joint recess will be mortared and painted with coal tar epoxy in the field, the pipe supplier shall not paint the inside vertical surfaces at the ends of the pipe. When the inside joints will not be mortared in the field, the pipe supplier shall paint the inside vertical concrete or mortar surfaces at each end of the pipe.
f. The paint shall be extended continuously over the front lip of the steel spigot ring and a minimum of two inches onto the sealing surface of unrestrained bell rings so that all interior joint surfaces which can be exposed to the fluid inside the pipe are coated.
E. Steel pipe.
1) Steel pipe shall meet the requirements ofASTMA-139 grade B,AWWA C-200 and shall be coal tar lined three thirty-seconds-inch in accordance with AWWA C-203. The outer coating shall be sand/grit blasted, primed to Federal Specification TTP-86C. Pipe shall have a minimum wall thickness of 0.250 inches.
History
(Ord. No. 2014-18, § 2, 8-21-2014; Ord. No. 2019-0516-02, 5-16-2019)