A. General. 1) Precast concrete manholes shall consist of precast reinforced concrete sections with eccentric, (or flat slab for shallow manholes) top section and a base section conforming to the typical manhole details as shown on the standard detail drawings in chapter 112 of this UDC. 2) The wall thickness shall not be less than five inches. 3) Manholes over 12 feet deep shall be placed on a reinforced slab. 4) Flat top manholes will be approved only if the need for such can be demonstrated by the design engineer. 5) All manholes shall be water tight when completely built. 6) Safety platforms shall be constructed in manholes in accordance with OSHA regulations and the details in these specifications. B. Manhole sections. Precast manhole sections shall be manufactured, tested, and marked in accordance with latest provisions of ASTM C478. C. Manhole sections joints. Joints of the manhole sections shall be of the tongue-and-groove type, sections shall be joined using O-ring gaskets, flexible plastic gaskets conforming to the applicable provisions of ASTM C433, latest revision, or an approved bituminous mastic joint material. D. Life holes. 1) Each section of the precast manhole shall have not more than two holes for the purpose of handling and laying. 2) These holes shall be sealed with cement mortar using one part portland cement to two parts clean sand, meeting ASTM C144, latest revision. E. Manhole steps. 1) Manhole steps conforming to the applicable provisions ofASTM C478, latest edition, shall be of #4 steel reinforcing bars covered with Polypropylene Plastic or rubber and shall be supplied with depth rings and other necessary appurtenances. 2) Steps shall be similar to and of an equal quality to the "PS1-PF" by M. A. Industries, Inc. of Peachtree City, Georgia. 3) The step shall be factory built into the precast sections. 4) See the standard details in chapter 112 for a typical manhole step detail. F. Pipe holes. 1) Holes in precast bases to receive sewer pipe shall be precast at the factory at the required locations and heights. 2) Knocking out of holes in the field is not permitted, however holes can be cored in the field with a coring machine. 3) All man holes shall have Kor-N-Seal (or equal) rubber boots for all pipe entries/exits. G. Bases and inverts. 1) Manhole bases and inverts shall be constructed of 2,500 psi concrete in accordance with details on standard detail drawings in chapter 112 of this UDC and the trough shall have the same cross-section as the sewers which it connects. 2) The manhole base and invert shall be carefully formed to the required size and grade by gradual and even changes in sections. 3) Changes in direction of flow through the sewer shall be made to a true curve with as large a radius as the size of the manhole will permit. 4) The minimum drop through a manhole shall be 0.1 foot. H. Manhole foundation. The manhole base shall be set upon a six-inch compacted (minimum thickness) mat of #57 crushed stone. I. Brick. 1) Brickwork required to complete the precast concrete manhole shall be constructed using one part portland cement to two parts clean sand, meeting ASTM C144, thoroughly mixed to a workable plastic mixture. 2) Brickwork shall be constructed in a neat and workmanlike manner. 3) Cement mortar shall be used to grout interior exposed brick joints and faces. 4) No more than three courses of brick with nine-inch maximum total depth of bricks may be used to adjust manhole covers. J. Frame and cover. 1) The cast iron frame for the manhole cover shall be set at the required elevation and properly anchored to the masonry. 2) Frames and covers shall be Neenah R-1776 or equal in compliance with the latest edition of ASTM 48. 3) Where manholes are constructed in paved areas, the top surface of the frame and cover shall be tilted, if necessary, to conform to the exact slope, crown and grade of the existing adjacent pavement. 4) In areas where manhole tops may be submerged by street runoff or high flood waters, the manhole lid shall be "self-sealing." 5) All covers shall have "SEWER" printed on them. K. Masonry work. 1) Masonry work shall be allowed to set for a period of not less than 24 hours. 2) All loose or waste material shall be removed from the interior of the manhole. The manhole cover then shall be placed and the surface in the vicinity of the work cleaned off and left in a neat and orderly condition. L. Location. 1) Manholes shall be installed, as follows: a. At the end of each line. b. At all changes in grade, size, or alignment. c. At all intersections. d. At distances normally not greater than 350 feet. 2) Spacing for eight-inch sewers can be more than 350 feet but not more than 400 feet and will be allowed only in isolated cases when, in the opinion of the reviewing engineer, it is impractical to install an additional manhole and when the extra distance will not impede maintenance of the line. Manhole spacing in sewers ten inches and larger will conform to Ten State Standards. In no circumstance will a spacing of greater than 300 feet be allowed when the slope exceeds ten percent cleanouts may be used only for special conditions and shall not be substituted for manholes nor installed at the ends of laterals greater than 150 feet in length. Manholes in cross-country areas shall be elevated so that the top is 18 inches above ground. M. Drop manholes. 1) A drop pipe shall be provided for a sewer entering a manhole at an elevation of more than two feet above the manhole invert. 2) The drop pipe shall be of ductile iron materials. 3) All out-side 90 degree elbows shall have thrust block poured below the elbow. 4) "Outside drop manhole" will be noted on the construction plans at any time the drop exceeds two feet. Where the difference in elevation between the incoming sewer and the manhole invert is less than two feet, the invert shall be sloped to prevent solids deposition.