--- title: Canton Zoning Ordinance, Sec. 114-129. Water and wastewater connections collection: local-codes id: local-code:canton/zoning/114-129 cite_as: Canton, Ga., Zoning Ordinance § 114-129 canonical_url: https://georgiacommons.org/code/local/canton/zoning/114-129 md_url: https://georgiacommons.org/code/local/canton/zoning/114-129.md text_url: https://georgiacommons.org/code/local/canton/zoning/114-129/text source_url: https://library.municode.com/ga/canton date: 2026-11-11 status: active jurisdiction: city:canton jurisdiction_name: Canton place_fips: "1312988" corpus_version: local-codes-canton-bb716bdc4821 publisher: Georgia Commons, an independent project of Georgia Civic Data. Not the State of Georgia. Not legal advice. up: https://georgiacommons.org/code/local/canton/zoning/~part-iii/~chapter-114/~article-iii.md previous: https://georgiacommons.org/code/local/canton/zoning/114-128.md next: https://georgiacommons.org/code/local/canton/zoning/114-130.md index: https://georgiacommons.org/code/local/canton.md branch: zoning edition: As published by Municode, retrieved 2026-11-11 edition_date_kind: retrieved source_publisher: Municode version_id: local-code:canton/zoning/114-129@2026-11-11-de4c0d594a --- # Canton Zoning Ordinance, Sec. 114-129. Water and wastewater connections > As published by Municode, retrieved 2026-11-11 > The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included. Part of: Part III - DEVELOPMENT CODE / Chapter 114 / Article III - CONSTRUCTION STANDARDS (a) Construction procedures. Construction procedures for water and wastewater connections are as follows: (1) All pavement cuts shall be made by sawing prior to excavation to eliminate uneven and ragged edges. (2) All backfill beneath roads, sidewalks or other paved areas shall be compacted to 95 percent standard proctor using mechanical tamping equipment in six-inch lifts. It shall be the responsibility of the person making the water or sewer connection to demonstrate to the city manager or his representative that 95 percent compaction has been obtained. (see development regulation 804.02(c), (d), (e) and (f)). (3) Final asphalt patches shall match the existing pavement type, quality and thickness as closely as possible. Special care shall be exercised to match existing slopes and grades for a smooth transition (see development regulation 804.02(g) in appendix B). (b) Inspection of connections by city. The applicant for a building sewer connection permit shall notify the water and sewer department manager when the building sewer is ready for inspection and connection to the city wastewater system. The connection and testing shall be made in the presence of the water and sewer department manager or his representative. A three-day notice is required. (c) Guarding excavations. All excavations for building sewer installation shall be adequately guarded with barricades and lights in compliance with all OSHA and state department of transportation requirements so as to protect the public from hazard. Streets, sidewalks, parkways and other public property disturbed in the course of the work shall be restored to a good as new condition in a manner satisfactory to the city. ## History (Ord. No. 2017-0921-01, § 1, 9-21-2017)