7.11.01. Application Procedure

About this text

  • As published by Municode, current through 2025-11-03
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

A. Applications for stormwater management permits shall be filed with the City Engineer.

Permit applications shall include the items set forth in Section 7.06.00 of this article (two

(2) copies of the stormwater management plan and the inspection maintenance agreement, if applicable, shall be included).

B. The City Engineer shall notify the applicant in writing within 30 days of receipt of the completed application whether the application, stormwater management plan, and inspection and maintenance agreement are approved or denied.

C. If the permit application, stormwater management plan or inspection and maintenance agreement are denied, the written notification from the City Engineer shall specify the reasons for the denial, and the applicant may then revise any item not meeting the requirements hereof and resubmit the same. Such resubmittal shall be treated as a new application; however, no new application fee shall be required.

D. Upon a finding by the City Engineer that the stormwater management permit application, stormwater management plan, and inspection and maintenance agreement, if applicable, meet the requirements of this article, the City Engineer shall issue a stormwater management permit for the land development project, provided all other legal requirements for the issuance of such permit have been met.

E. Notwithstanding the issuance of the stormwater management permit, in conducting the land development project, the applicant or other responsible person shall be subject to the following requirements:

1. The applicant shall comply with all applicable requirements of the approved plan and this article and shall certify that all land development will be completed according to the approved plan.

2. The land development project shall be conducted only within the area specified in the approved plan.

3. No changes may be made to an approved stormwater management plan without review and written approval by the City Engineer.

4. Upon completion of the land development project, the applicant or other responsible person shall submit the engineer's report and certificate and as-built plans pursuant to Section 7.14.02 of this Article.

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:carrollton/zoning/7.11.01@2025-11-03-fde497be7a

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Carrollton Zoning Ordinance, 7.11.01. Application Procedure | Georgia Commons