3.02.00 WATER RESOURCE DISTRICTS

3.02.07 Water Supply Watershed District

2. Reservoir management plan criteria.

a. Prohibitions or restrictions on all or some of the following recreational uses (swimming, fishing, boating, docks, and public access) are addressed in the City's DNR-approved reservoir management plan dated June 1992. These restrictions were developed to protect the water quality of the three reservoirs for drinking purposes while optimizing their recreational benefits.

b. Because the three reservoirs were placed in use at different times over the past forty years, use restrictions and buffer requirements vary for each reservoir.

c. All new reservoirs shall have a buffer for a distance of 150 feet from the reservoir boundary and shall have prohibitions or restrictions on all or some of the recreational uses listed above, to protect the water quality for drinking purposes.

d. At such time in the future, if the land use changes at Lake Carroll result in a more concentrated use of the lake, then the City will address imposing more restrictive recreational measures in order to continue to preserve the water quality of the reservoir.

3. Small water supply watershed criteria.

The following criteria apply to all locations within the City's small water supply watershed.

a. New sanitary landfills are allowed only if they have synthetic liners and leachate collection systems.

b. New hazardous waste treatment or disposal facilities are prohibited.

c. The impervious surface area, including all public and private structures, utilities, or facilities, of the entire water supply watershed shall be limited to twenty-five (25%) percent, or existing use, whichever is greater.

d. New facilities, which handle hazardous materials of certain types and in certain amounts as determined by the Department of Natural Resources, shall perform their operations on impermeable surfaces having spill and leak collection systems as prescribed by the Department of Natural Resources.

E. Exemptions.

The following uses are exempt from the stream corridor buffer and setback requirements if they meet the stipulated conditions:

1. Utilities.

a. Utilities shall be located as far as reasonably possible from the stream bank and shall not impair the quality of the drinking water system.

b. Utilities shall be installed and maintained without changing the integrity of the buffer and setback areas as best as reasonably possible.

2. Forestry, agricultural and mining activities.

a. Agricultural activities involving the planting and harvesting of crops are exempted if they conform to the best management practices established by the state Department of Agriculture and USDA.

b. Forestry activities must conform to the best management practices established by the state forestry commission.

c. Mining activities permitted by the Department of Natural Resources under the Surface Mining Act.

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:carrollton/zoning/appendix-b-article-3-article-3-25@2025-11-03-5816039884

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Carrollton Zoning Ordinance, Article 3 (Appendix B, no. 25 so numbered). PROTECTION OF NATURAL, ENVIRONMENTAL AND HISTORIC RESOURCES | Georgia Commons