6.11.00 DECELERATION LANES AND TURN LANES

6.14.00 WATER SUPPLY

A. Public water service shall be provided to every lot in every subdivision and to every development for both domestic use and fire protection if public water is available or under bid or contract to be available within 1,000 feet of the subdivision or development.

B. All water system improvements and their installation shall meet the adopted standards of the Carrollton Water and Wastewater Departments. A contractor approved by the City of Carrollton shall install all elements of the water system, including mains, valves, service laterals through the curb line, and fire hydrants at the developers expense.

6.15.00 FIRE HYDRANTS

A. Fire hydrants are required in all subdivisions and development projects served by a public water system.

B. Fire hydrants as specified by the Fire Department and the City of Carrollton shall be located every five-hundred (500) feet and/or at every intersection, whichever is closer.

6.16.00 SANITARY SEWERAGE DISPOSAL

A. When in the written opinion of the Carroll County Health Department and the City Engineer, public sanitary sewers are within reasonable access of the subdivision, the subdivider shall provide sanitary sewer services to each lot within the bounds of the subdivision. All sewer service lines in the subdivision shall be installed by the subdivider in accordance with the Design and Construction Standards.

B. When in the written opinion of the City of Carrollton a public sanitary sewer is not acceptable, an alternate method of sewage disposal for each lot may be used when in compliance with the Carroll County Health Department requirements. A community sewage disposal system may not be used.

C. Whenever the installation of a sanitary system is required as provided by these regulations, no new street shall be paved without such sewer being first installed in accordance with the requirements of the Georgia Department of Human Resources sewer specifications and the City of Carrollton Design and Construction Standards.

6.17.00 LOCATION OF UTILITIES AND STREET CUTS

6.17.01 Location of [U]tilities in [S]treets

A. Above-ground [U]tilities.

Street light poles, junction boxes, transformers and other public or private utility structures placed above ground within a public street right-of-way or private street easement must meet set-back criteria and clear zone distance criteria based on the latest edition of the Roadside Design Guide, by theAmericanAssociation of State Highway and Transportation Officials, or be located at least nine (9) feet back from the back of the street curb (or edge of pavement) and one (1) foot back from the edge of any sidewalk, whichever is farthermost from the roadway.

B. Underground Utilities.

1. All electric, telephone, cable TV and other wires shall be placed underground in any major subdivision, and in any multi-family or non-residential development.

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:carrollton/zoning/appendix-b-article-6-article-6-20@2025-11-03-251c073a61

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Carrollton Zoning Ordinance, Article 6 (Appendix B, no. 20 so numbered). INFRASTRUCTURE IMPROVEMENTS | Georgia Commons