7.07.01. Concept Plan Requirements
About this text
- As published by Municode, current through 2025-11-03
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
5. Where the existing development is to be redeveloped, the applicant should attempt to make every reasonable effort to provide water quality and detention for the total land area of the redeveloped site, which may include but not be limited to underground detention and subsurface water quality treatment.
6. Stormwater management system. The description, scaled drawings, and design calculations for the proposed post-development stormwater management system shall include a map and/or drawing of the stormwater management facilities, including the location of non-structural site design features and the placement of existing and proposed structural stormwater controls, including design water surface elevations, storage volumes available from zero to maximum head, location of inlet and outlets, location of bypass and discharge systems, and all orifice/restrict or sizes; a narrative describing how the selected structural stormwater controls will be appropriate and effective; cross-section and profile drawings and design details for each of the structural stormwater controls in the system, including supporting calculations to show that the facility is designed according to the applicable design criteria; a hydrologic and hydraulic analysis of the stormwater management system for all
applicable design storms (including stage-storage or outlet rating curves, and inflow and outflow hydrographs); documentation and supporting calculations to show that the stormwater management system adequately meets the post-development
stormwater management performance criteria in Section 7.13.00 of this article;
drawings, design calculations, elevations and hydraulic grade lines for all existing and proposed stormwater conveyance elements, including stormwater drains, pipes,
culverts, catch basins, channels, swales and areas of overland flow; and where applicable, a narrative describing how the stormwater management system corresponds with any watershed protection plans and/or local greenspace protection plan.
7. Post-development downstream analysis. A downstream peak flow analysis, which includes the assumptions, results and supporting calculations to show safe passage of post-development design flows downstream. The analysis of downstream conditions in the report shall address each and every point or area along the project site's boundaries at which runoff will exit the property. The analysis shall focus on the portion of the drainage channel or watercourse immediately downstream from the
project. This area shall extend downstream from the project to a point in the drainage basin where the project area is ten (10) percent of the total basin area. In calculating runoff volumes and discharge rates, consideration may need to be given to any
planned future upstream land use changes. The analysis shall be in accordance with the Georgia Stormwater Management Manual.
8. Construction-phase erosion and sedimentation control plan. An erosion and sedimentation control plan which satisfies the requirements of Article 3 of this UDO. The plan shall also include information on the sequence/phasing of construction and temporary stabilization measures and temporary structures that will be converted into permanent stormwater controls.
9. Landscaping and open space plan. A detailed landscaping and vegetation plan describing the woody and herbaceous vegetation that will be used within and adjacent to stormwater management facilities and practices. The landscaping plan must also include: the arrangement of planted areas, natural and greenspace areas and other landscaped features on the site plan; information necessary to construct the landARTICLE 7 STORMWATER MANAGEMENT