In addition to meeting the requirements to obtain a Special Use Permit under this UDC, any solar farm shall meet the following requirements: A. A solar farm installation shall be constructed on five or more acres in agricultural zoning districts. B. A solar farm connected to the utility grid shall provide a Hproof of concept letterH from the local utility company acknowledging the solar farm will be interconnected to the utility grid in order to sale electricity to the public utility entity. C. The design of the solar farm shall adhere to existing structural height requirements. If the solar farm requires a roof mounting on buildings on the property, the roof mounted installation may not exceed the maximum principal building height or accessory building height specified for the building type in the underlying zoning district. D. The design of the solar farm shall adhere to the setback requirements of the underlying zoning district. If the solar farm will be constructed by the utilization of ground mounting, then a ground mounting plan and process must be submitted during the county application process. The ground mounting plan may consist of standard solar manufacturer installation plans and processes for ground mounting. E. The operation of the solar farm shall comply with the following: 1) Equipment shall be screened and fenced from adjacent property to restrict unauthorized access. Screening shall consists of a minimum 8 foot opaque fence with the addition of shrubbery, trees or an earthen berm as may be required to comply with the view shed/glare requirements. 2) Solar equipment shall not be located within the minimum front yard or setback of the underlying zoning district. 3) Solar panels shall not be placed in the vicinity of any airport in a manner that would interfere with airport flight patterns. Acknowledgement from the Federal Aviation Administration may be necessary. 4) All power transmission lines from a ground mounted solar farm shall be located underground after connection from the solar panel combiners to the interconnection point. 5) A solar energy system shall not be used to display signage, streamers, pennants, spinners, reflectors, ribbons, tinsel, balloons, flags, banners or similar materials, with the exception that the manufacturers' or installers' identification and appropriate warning signage shall be posted at the site in a clearly visible manner. 6) The local utility provider shall be contacted to determine grid interconnection and net metering policies. 7) Viewshed/glare—The applicant shall demonstrate that the proposal will not have an adverse effect on neighboring properties by providing aerials of the site, graphic renderings of the project, and/or pictures from the site of surrounding parcels demonstrating sight lines. Appropriate vegetated buffers and/or plantings may also be required to help limit the visual impact of the site and possible glare issues. F. The following requirements shall be met for building/development permit applications: 1) A descriptive plot plan including setbacks, panel sizes, locations of property lines, building, and road rights-of-way. 2) Any other relevant studies, reports, certificates and approvals as may be reasonably requested by the Planning and Zoning Office. 3) A stormwater management study shall be provided to ensure compliance with local BMPs. G. The following requirements shall be met for decommissioning: 1) Solar energy farms which have not been in active and continuous service for a period of one year shall be removed at the owners or operators expense. 2) The site shall be restored to as natural condition as possible within six months of the removal.