(a) In the event the building or site development plans are denied because revisions are required, the applicant may submit revised plans. If the applicant fails to submit revisions within 180 days of filing the completed application, the application and site plans shall be deemed withdrawn. If revised plans are not approved within 180 days of filing the completed application, the plan(s) shall be deemed withdrawn. The plans will not expire within 180 days if the inactivity is a result of a pending review from an external agency outside the City or applicant's control. (b) In the event that a permit has not been issued for approved plans, building and development plans shall expire within 180 days of notice of plan approval.