Chamblee · Zoning Ordinance

Appendix A - UNIFIED DEVELOPMENT ORDINANCE / Title 3 - DEVELOPMENT AND PERMITTING / Chapter 330 - FLOODPLAIN MANAGEMENT

Section 330-3. Permit procedures and requirements.

About this text

  • As published by Municode, retrieved 2026-11-14
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

(a) Permit application requirements. No owner or developer shall perform any development activities on a site where an area of special flood hazard or area of future-conditions flood hazard, as defined in Chapter 110, is located without first meeting the requirements of this chapter prior to commencing the proposed activity. Unless specifically excluded by this chapter, any landowner or developer desiring a permit for a development activity shall submit to the City a permit application on a form provided by the City for that purpose. No permit will be approved for any development activities that do not meet the requirements, restrictions and criteria of this chapter.

(b) Floodplain management plan requirements. An application for a development project with any area of special flood hazard or area of future-conditions flood hazard located on the site will be required to include a floodplain management/flood damage prevention plan. This plan shall include the following items:

(1) Site plan drawn to scale, which includes but is not limited to:

a. Existing and proposed elevations of the area in question and the nature, location and dimensions of existing and/or proposed structures, earthen fill placement, amount and location of excavation material, and storage of materials or equipment;

b. For all proposed structures, spot ground elevations at building corners and 20-foot or smaller intervals along the foundation footprint, or one-foot contour elevations throughout the building site;

c. Proposed locations of water supply, sanitary sewer and utilities;

d. Proposed locations of drainage and stormwater management facilities;

e. Proposed grading plan;

f. Base flood elevations and future-conditions flood elevations;

g. Boundaries of the base flood floodplain and future-conditions floodplain;

h. If applicable, the location of the floodway; and

i. Certification of the above by a professional engineer licensed in the State of Georgia or surveyor.

(2) Building and foundation design detail, including but not limited to:

a. Elevation in relation to mean sea level (or highest adjacent grade) of the lowest floor, including basement, of all proposed structures;

b. Elevation in relation to mean sea level to which any nonresidential structure will be floodproofed;

c. Certification that any proposed nonresidential floodproofed structure meets the criteria in Subsection 330-5(b)(2);

d. For enclosures below the base flood elevation, location and total net area of foundation openings as required in Subsection 330-5(a)(5); and

e. Design plans certified by a professional engineer licensed in the State of Georgia or architect for all proposed structure(s).

(3) Description of the extent to which any watercourse will be altered or relocated as a result of the proposed development;

(4) Hard copies and digital files of computer models, if any, copies of work maps, comparison of pre- and post-development conditions base flood elevations, future-conditions flood elevations, flood protection elevations, special flood hazard areas and regulatory floodway widths, flood profiles and all other computations and other information similar to that presented in the FIS;

(5) Copies of all applicable state and federal permits necessary for proposed development; and

(6) All appropriate certifications required under this Chapter.

(c) The approved floodplain management/flood damage prevention plan shall contain certification by the applicant that all development activities will be done according to the plan or previously approved revisions. Any and all development permits and/or use and occupancy certificates or permits may be revoked at any time if the construction and development activities are not in strict accordance with approved plans.

(d) Construction stage submittal requirements. For all new construction and substantial improvements on sites with a floodplain management/flood damage prevention plan, the permit holder shall provide to the Planning and Development Director a certified as-built elevation certificate or floodproofing certificate for nonresidential construction including the lowest floor elevation or floodproofing level immediately after the lowest floor or floodproofing is completed. A final elevation certificate shall be provided after completion of construction including final grading of the site. Any lowest floor certification made relative to mean sea level shall be prepared by or under the direct supervision of a registered land surveyor or professional engineer and certified by same. When floodproofing is utilized for nonresidential structures, said certification shall be prepared by or under the direct supervision of a professional engineer or architect and certified by same using the FEMA Floodproofing Certificate. This certification shall also include the design and operation/maintenance plan to assure continued viability of the floodproofing measures.

(e) Any work undertaken prior to approval of these certifications shall be at the permit holder's risk. The Planning and Development Director or his/her designee shall review the above-referenced certification data submitted. Deficiencies detected by such review shall be corrected by the permit holder immediately and prior to further work being allowed to proceed. Failure to submit certification or failure to make the corrections required hereby shall be cause to issue a stop work order for the project.

(f) Duties and responsibilities of the administrator. Duties of the Planning and Development Director or his/her designee shall include, but shall not be limited to:

(1) Review all development applications and permits to assure that the requirements of this chapter have been satisfied and to determine whether proposed building sites will be reasonably safe from flooding;

(2) Require that copies of all necessary permits from governmental agencies from which approval is required by federal or state law, including but not limited to, section 404 of the Federal Water Pollution Control Act Amendments of 1972, 33 U.S.C. § 1334, be provided and maintained on file;

(3) When base flood elevation data or floodway data have not been provided, then the Planning and Development Director or his/her designee shall require the applicant to obtain, review and reasonably utilize any base flood elevation and floodway data available from federal, state or other sources in order to meet the provisions of Section 330-4 and Section 330-5;

(4) Review and record the actual elevation in relation to mean sea level (or highest adjacent grade) of the lowest floor, including basement, of all new or substantially improved structures;

(5) Review and record the actual elevation, in relation to mean sea level to which any substantially improved structures have been floodproofed;

(6) When floodproofing is utilized for a nonresidential structure, the Planning and Development Director or his/her designee shall obtain certification of design criteria from a professional engineer or architect licensed in the State of Georgia;

(7) Notify affected adjacent communities and the Georgia Department of Natural Resources prior to any alteration or relocation of a watercourse and submit evidence of such notification to the Federal Emergency Management Agency (FEMA);

(8) Where interpretation is needed as to the exact location of boundaries of the areas of special flood hazard (e.g., where there appears to be a conflict between a mapped boundary and actual field conditions) the Planning and Development Director or his/her designee shall make the necessary interpretation. Any person contesting the location of the boundary shall be given a reasonable opportunity to appeal the interpretation as provided in this chapter. Where floodplain elevations have been defined, the floodplain shall be determined based on flood elevations rather than the area graphically delineated on the floodplain maps;

(9) All records pertaining to the provisions of this chapter shall be maintained in the office of the Planning and Development Director and shall be open for public inspection;

(10) Coordinate all FIRM revisions with the Georgia Department of Natural Resources and FEMA; and

(11) Review variance applications and make recommendations to City Council.

History

The history line the source prints at the end of the section.

(Ord. No. 743, 12-19-17; Ord. No. 757, 12-18-18)

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:chamblee/zoning/330-3@2026-11-14-d7f66899bb

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Chamblee Zoning Ordinance, Section 330-3. Permit procedures and requirements | Georgia Commons