(a) The following performance criteria shall be applicable to all stormwater management plans, unless otherwise provided for in this Article: (1) Stormwater Runoff Quality/Reduction: Stormwater Runoff Quality/Reduction shall be provided by using the following: a. For development with a stormwater management plan submitted before January 1, 2020, the applicant may choose either: (A) Runoff Reduction; or (B) Water Quality. b. For development with a stormwater management plan submitted on or after January 1, 2020, the applicant shall choose (A) Runoff Reduction and additional water quality shall not be required. If (A) Runoff Reduction has been determined to be infeasible using the Practicability Policy per 340-39(b), then (B) Water Quality shall apply for the remaining runoff from a 1.2 inch rainfall event and must be treated to remove at least 80% of the calculated average annual post-development total suspended solids (TSS) load or equivalent as defined in the GSMM. 1. Runoff Reduction - The stormwater management system shall be designed to retain the first 1.0 inch of rainfall on the site using runoff reduction methods, to the maximum extent practicable. 2. Water Quality - The stormwater management system shall be designed to remove at least 80% of the calculated average annual post-development total suspended solids (TSS) load or equivalent as defined in the GSMM for runoff from a 1.2 inch rainfall event. c. If a site is determined to be a hotspot as detailed in Section 300-3, the City may require the use of specific or additional components for the stormwater management system to address pollutants of concern generated by that site. (2) Stream channel protection. Protection of stream channels from bank and bed erosion and degradation shall be provided by using all of the following three approaches: a. Preservation, restoration and/or reforestation (with native vegetation) of the applicable stream buffer; b. Twenty-four-hour extended detention storage of the one-year, 24-hour return frequency storm event; these flows will not have an impact on upstream or downstream stream bank or channel integrity; c. Erosion prevention measures such as energy dissipation and velocity control. (3) Overbank flooding protection. Downstream overbank flood and property protection shall be provided by controlling (attenuating) the post-development peak discharge rate to at least 90 percent of the pre-development rate for the 25-year, 24-hour return frequency storm event. If control of the one-year, 24-hour storm under Subsection 340-39(a)(2) is exempted, then peak discharge rate attenuation of the two-year through the 25-year return frequency storm event must be provided. If structural stormwater controls are implemented within the stormwater management plan that promote infiltration, the City Engineer may allow the post-development peak discharge rate to not exceed the pre-development rate of the current existing condition, regardless of the amount of impervious area to be removed and replaced on-site. (4) Extreme flooding protection. Extreme flood and public safety protection shall be provided by controlling and safely conveying the 100-year, 24-hour return frequency storm event such that flooding is not exacerbated. (5) Structural stormwater controls. All structural stormwater management facilities shall be selected and designed using the appropriate criteria from the 2016 edition of the Georgia Stormwater Management Manual and the additional conditions and exceptions listed under Subsections 340-39(a)(5)a.—(a)(5)s. All structural stormwater controls must be designed appropriately to meet their intended function. For other structural stormwater controls not included in the 2016 edition of the Georgia Stormwater Management Manual, or for which pollutant removal rates have not been provided, the effectiveness and pollutant removal of the structural control must be documented through prior studies, literature reviews, or other means and receive approval from the City as described in Subsection 340-38(j) of this Article before being included in the design of a stormwater management system. In addition, if hydrologic or topographic conditions, or land use activities warrant greater control than that provided by the minimum control requirements, the City may impose additional requirements deemed necessary to protect upstream and downstream properties and aquatic resources from damage due to increased volume, frequency, and rate of stormwater runoff or increased nonpoint source pollution loads created on the site in question. a. All stormwater structural control measures are allowed except for alum treatment. b. Organic filter may only be used in space-limited applications that require enhanced removal capability, such as hotspots. The City Engineer shall meet with the applicant to make a determination if the site is space-limited. c. Underground sand filter and submerged gravel wetlands may only be used in space-limited applications. The City Engineer shall meet with the applicant to make a determination if the site is space-limited. d. Stormwater structural controls, which are designed to have a permanent pool of water, shall not include slopes in excess of 3:1, incorporate safety and/or aquatic benches as recommended in the stormwater design manual, and deter access to permanent pool by providing landscape on safety benches in order to reduce the potential for accidental drowning. The perimeter of all deep pool areas (four feet or greater in depth) should be surrounded by two benches: safety and aquatic. The safety bench shall extend outward from the normal pool elevation to the toe of the pond side slopes. The maximum slope of the safety bench shall be six percent. An aquatic bench shall extend inward from the normal pool edge with a maximum depth of 18 inches below the normal pool water surface elevation. The average widths of safety and aquatic benches shall be 15 feet. Fencing stormwater structural controls is not an allowed safety precaution. However, if City Council approves a deviation of this Article and allows fencing, fencing shall: be a minimum of six feet in height, allow free flow of runoff into the stormwater structural control measure(s), and include a gate of sufficient size to permit entrance of equipment for periodic maintenance. e. Side slopes for stormwater structural controls shall not exceed 3:1. The side slopes for stormwater structural controls that are designed to have a normal pool of water shall terminate on a safety bench. The safety bench may be waived by the Planning and Development Director upon recommendations received from review staff if slopes are 4:1 or greater. f. Retaining walls shall not be permitted as structural control or impoundment devices for dry detention ponds. A wall of no more than 18 inches in height above the permanent pool may be approved by the Planning and Development Director for this purpose in a stormwater pond. g. Retaining walls shall not be constructed within the side slopes of any stormwater facility. The Planning and Development Director may approve walls of no more than 18 inches within the side slopes of a stormwater pond if deemed to provide an amenity which focuses on the permanent pool of the stormwater pond. h. Planning and Development Director may grant a waiver upon recommendations received by review staff for retaining walls used as an outlet control structure, as long as the wall does not extend more than five feet on either side of the outside edge of weir/orifice for grade transitions to earthen berms. i. Standpipes and outlet control structures associated with structural stormwater controls shall be designed to provide measures to obstruct and/or soften views to standpipes and outlet control structures from streets and adjacent properties as deemed acceptable by City review staff. j. The footprint of stormwater ponds, stormwater wetlands, submerged gravel wetlands, and dry detention/dry extended detention basins shall be irregular in shape as deemed acceptable by City review staff to provide a more natural landscaping effect. k. Stormwater ponds within residential subdivisions shall be located on a separate lot that does not contain a dwelling unit. Stormwater ponds may be located within a designated common area within a subdivision or on unbuildable lots. l. The footprint of stormwater ponds, stormwater wetlands, submerged gravel wetlands, and dry detention/dry extended detention basins shall not encroach in the space between rights-of-way and portions of buildings that face right-of-way and/or between multiple buildings on a site. All other stormwater structural control measures listed within the stormwater design do not have any site location restrictions. However, stormwater ponds, stormwater wetlands, and submerged gravel wetlands designed as amenity features may be waived of these location restrictions upon council's review and approval of the amenity concept. See Subsection 340-38(i) for amenity pond/wetland approval process. m. All stormwater structural controls that require ground cover must meet the landscaping and aesthetics guidance of the 2016 edition of the Georgia Stormwater Management Manual. n. Measures shall be provided to aid in containing mulch within bioretention areas during storm events. o. No side walls of any stormwater structural control intended to be underground, such as underground sand filter, gravity (oil grit) separator, and underground detention, shall be allowed. The tops of these units shall not be exposed in nonpaved areas, except for inlets and access manholes associated with these units. p. The total suspended solids removal rate associated with pervious concrete and modular paver systems may be 80 percent if: runoff from pervious surface is avoided to the pervious pavement system; manufacturer can submit proven documentation of maintenance measures to prevent clogging and methods to easily unclog system; and owner agrees to implement these maintenance measures recommended by manufacturer. q. Stormwater structural control measures that have a permanent pool of water shall include mosquito control measures. r. The following landscaping requirements shall apply to stormwater ponds: 1. The bottom and sides of detention ponds shall be planted with fast-germinating, erosion-controlling vegetation, continuous over the entire surface of disturbed soils both inside and outside of the pond. 2. Larger-growing species of perennial plants shall be interplanted in the wet areas of the pond (up to the 25-year storm inundation line) on minimum ten-foot centers, that are capable of thriving in intermittently wet and dry soils and will provide food and habitat for birds and other wildlife. 3. Trees are prohibited within or on the outer slopes of detention ponds in order to prevent damage to the pond structure. 4. If located within a permanent buffer, the screening requirements for permanent buffers as regulated by Section 320-12 shall also apply. s. Applicants shall consult the 2016 edition of the Georgia Stormwater Management Manual for guidance on the factors that determine site design feasibility when selecting and locating a structural stormwater control. (6) Stormwater credits for nonstructural measures. The use of one or more site design measures by the applicant may allow for a reduction in the water quality treatment volume required under Subsection 340-39(a)(1). The applicant may, if approved by the City, take credit for the use of stormwater better site design practices and reduce the water quality volume requirement. For each potential credit, there is a minimum set of criteria and requirements which identify the conditions or circumstances under which the credit may be applied. The site design practices that qualify for this credit and the criteria and procedures for applying and calculating the credits are included in the 2016 edition of the Georgia Stormwater Management Manual. (7) Drainage system guidelines. a. Stormwater conveyance facilities, which may include, but are not limited to, culverts, stormwater drainage pipes, catch basins, drop inlets, junction boxes, headwalls, gutter, swales, channels, ditches, and energy dissipaters shall be provided when necessary for the protection of public right-of-way and private properties adjoining project sites and/or public rights-of-way. All new development and redevelopment sites that generate concentrated flow will be required to connect to existing public underground storm drainage conveyance system(s). However, if City Engineer determines that connection to an existing public underground storm drainage conveyance system is not feasible, all new development and redevelopment sites shall discharge into a stabilized channel from the point of release to the point of connection to the public storm drainage conveyance system. Also, all outlets from structural stormwater controls must be located a minimum distance from the project boundary to provide adequate dissipation of energy as described by the 2016 edition of the Georgia Stormwater Management Manual. Under no circumstances shall the outlet from structural stormwater controls be any closer than ten feet to the site boundary. b. Stormwater conveyance facilities that are designed to carry runoff from more than one parcel, existing or proposed, shall meet the following requirements: 1. Methods to calculate stormwater flows shall be in accordance with the 2016 edition of the Georgia Stormwater Management Manual; 2. All culverts, pipe systems and open channel flow systems shall be sized in accordance with the stormwater management plan using the methods included in the 2016 edition of the Georgia Stormwater Management Manual; 3. Design and construction of stormwater conveyance facilities shall be in accordance with the criteria and specifications found in the 2016 edition of the Georgia Stormwater Management Manual; and 4. Provide drainage easement for the stormwater conveyances that are designed to carry runoff from more than one parcel. The drainage easement widths shall be as listed in the following Table of Minimum Easement Widths in Feet, unless the Public Works Director approves otherwise: Table of Minimum Easement Widths in Feet Pipe Size (ft.) | Maximum Pipe Invert Depth (ft.) 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 1.25 | 20 | 20 | 20 | 20 | 20 | 25 | 25 | 30 | 30 | 30 | 35 | 35 | 40 1.50 | 20 | 20 | 20 | 20 | 20 | 25 | 25 | 30 | 30 | 30 | 35 | 35 | 40 2.00 | 20 | 20 | 20 | 20 | 20 | 25 | 25 | 30 | 30 | 30 | 35 | 35 | 40 2.50 | 20 | 20 | 20 | 20 | 25 | 25 | 25 | 30 | 30 | 35 | 35 | 35 | 40 3.00 | 20 | 20 | 20 | 20 | 25 | 25 | 25 | 30 | 30 | 35 | 35 | 35 | 40 3.50 | 20 | 20 | 20 | 25 | 25 | 30 | 30 | 30 | 35 | 35 | 40 | 40 4.00 | 20 | 20 | 20 | 25 | 25 | 30 | 30 | 30 | 35 | 35 | 40 | 40 4.50 | 20 | 25 | 25 | 25 | 30 | 30 | 35 | 35 | 35 | 40 | 40 5.00 | 20 | 25 | 25 | 25 | 30 | 30 | 35 | 35 | 35 | 40 | 40 5.50 | 25 | 25 | 30 | 30 | 30 | 35 | 35 | 40 | 40 | 40 6.00 | 25 | 25 | 30 | 30 | 30 | 35 | 35 | 40 | 40 | 40 (8) Dam design guidelines. Any land-disturbing activity that involves a site which proposes a dam shall comply with the Georgia Safe Dams Act and Rules for Dam Safety, as applicable. (b) Determination of Infeasibility for the Practicability of Runoff Reduction. (1) The City's Planning and Development Department will rule on a determination of Infeasibility for an application under this title upon preparation of a report by a design professional as defined in 310-4(e). The report shall be prepared in accord with 340-38(c) and address the minimum criteria as outlined in the following table: Table 2-1. Gl Infeasibility Criteria and Required Documentation Condition | Benchmark | Testing | Documentation Soil Infiltration Rate | 0.5 inch/hour | 1. Infiltration testing in a saturated condition 2. Soil test using a hand auger, test pit, or drilling equipment. On average, at least one test for every two acres should be completed, but in no case less than two locations per development site. | Infiltration test(s), soil boring log(s), and report of results as interpreted by a Professional Engineer, Professional Geologist, or Soil Scientist licensed in Georgia. Water Table | Seasonally-high water table (within zero to two feet of the bottom of the infiltration practice. | 1. Groundwater depth at an average of at least one location for every two acres, but in no case less than two locations per developed site. | Soil boring log(s) and report with results of the seasonally-high water table assessment as interpreted by a Professional Engineer, Professional Geologist, or Soil Scientist licensed in Georgia. Bedrock | Shallow bedrock (within zero to two feet of the bottom of the infiltration practice. Bedrock is defined as material which cannot be excavated except by drilling or blasting. | 1. Bedrock depth at an average of at least one location for every two acres, but in no case less than two locations per development site. | Soil boring log(s) and report with results of the shallow bedrock assessment as interpreted by a Professional Engineer, Professional Geologist, or Soil Scientist licensed in Georgia. Extreme Topography | Anything steeper than 3:1 slope for more than 50% of the site. | 1. Site survey | Site survey showing 50% of the site is steeper than 3:1 slopes as interpreted by a Professional Engineer or Land Surveyor licensed in Georgia. Karst Topography | Any of the existing condition is karst. | 1. Geologic survey map and/or evidence of ground subsidence, indicative of karst topography. | Report developed by a Professional Engineer, Professional Geologist, or Soil Scientists licensed in Georgia. Hotspot/Contamination | Reasonable suspicion that previous uses of the site have resulted in soil contamination. | 1. Phase II Environmental Assessment | Phase II Environmental Assessment Report (2) The City is to provide a determination of either acceptance or rejection. If rejected, the applicant may appeal in accord with 310-25. (3) Approval of the permit will constitute final approval of the Determination of Infeasibility.