(1) Preliminary Plats. Preliminary approval grants the developer a maximum time of 18 months within which he shall submit his improvement plan and final plat for approval unless a time extension is granted before the expiration of the 18 month period. If such time extension is granted, it shall be for not more than 12 additional months. Failure to submit improvement plans and final plat within this time period, including extension if any, shall invalidate preliminary plat approval and require resubmission of preliminary plat. (2) Improvement Plan Approvals. Improvement plan approvals are valid for 24 months. If the subdivision is sold prior to completion and final platting, a mandatory review by the DRC shall be required. (3) Building Permit. Any building permit shall become void if the work involved has not begun within six months after the date of issuance of the permit or if the work or development authorized by such permit is suspended or abandoned for a period of six months after the work of development is commenced; provided that extensions of time and periods not exceeding six months each may be allowed in writing by the Administrator. (4) Land Disturbing Permit. If construction described in a land-disturbing permit has not commenced within six months from the date of issuance of the permit, the permit shall expire. If construction described in a land disturbing permit is suspended or abandoned after work has commenced, the permit shall expire six months after the date that work ceased. (5) Extensions. The time period for which a permit is valid may be extended for up to six months where an application for such extension is filed and such extension has been granted in writing by the Zoning Administrator.