(a) Enforcing officer. The provisions of this chapter shall be administered and enforced by the director. The director and his designee shall have the right to enter upon any premises for the purpose of making inspections of buildings or premises necessary to carry out the duties of the director in the enforcement of this chapter. In addition, the director or his designee shall issue building permits, and make and maintain records thereof, issue certificates of occupancy, and make and maintain records thereof, and conduct inspections as set forth in this chapter, and other such inspections as deemed necessary to ensure compliance with this chapter.

(b) Building permits required. It shall be unlawful to commence the excavation for, or the construction of, any building or structure, including accessory structures, or to commence the moving, alteration or repair of any structure,

including accessory structures, until the county director has issued a building permit for such work which contains a statement that the plans, specifications and intended use of such structure conforms with the provisions of this chapter in all respects.

(c) Application for building permit. Application for a building permit shall be made in writing to the director, on forms provided for

such purpose. It shall be unlawful for the director to approve any plans, or issue a building permit for any excavation or construction until

he or his designee has inspected such plans in detail, and found them to be in conformity with this chapter. The director may require that an application for a building permit for excavation, construction, moving or alteration be accompanied by a plan or plat drawn to scale, and showing the following, in sufficient detail, to enable the director to ascertain whether the proposed excavation, construction, moving or alteration is in conformance with this chapter:

(1) The actual shape, location and dimensions of the lot to be built upon.

(2) The shape, height, use and location on the lot of buildings or structures to be erected or altered.

(3) The size, location and use of any existing building or structure on the lot.

(4) If residential, the number of dwelling units the building is designed to accommodate.

(5) The setback lines of buildings on adjoining lots.

(6) The layout of off-street parking and unloading spaces.

(7) The signature of the county health officer approving the proposed location of the septic tank and field lines, provided public sewerage is not available at such location.

(8) Such other information concerning the lot or adjoining lots as may be essential in determining whether the provisions of this chapter are being observed.

If the proposed excavation, construction, moving or alteration, as set forth in the application for a building permit, is in conformity with the provisions of this chapter, the director shall issue a building permit for such excavation, construction, moving or alteration. If the application for a building permit is not approved, the director

shall state in writing on the application the cause for such disapproval. Issuance of a building permit shall not be construed as waiving any provision of this chapter, and building permits

shall be void after 12 months from date of issue of such building permit, unless substantial progress on the project has been made by that time.

(d) Certificate of occupancy. No land or building, or other structure or part thereof, erected, moved or altered in its use shall be occupied or

used until the building official for the county, the county engineer or the director has signed a certificate of occupancy. A certificate of occupancy shall be issued only upon compliance with the provisions of this chapter. If the certificate of occupancy is not granted upon request, the building official, the engineer or the director shall state in writing the reasons why the certificate of occupancy was not granted.

History

The history line the source prints at the end of the section.

(Code 1979, § 2-16-82; Ord. No. 99-14, § 1, 11-16-1999)

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:columbia-county/zoning/90-178@2026-02-17-12446fbf9f

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Columbia County Zoning Ordinance, Sec. 90-178. Enforcement | Georgia Commons