A. Above-ground Utilities. Telephone poles, street light poles, telephone junction boxes and other public or private utility structures placed above ground within a street right-of-way must be at least nine feet back from the back of the street curb or edge of pavement and at least one foot back from the edge of any sidewalk, whichever is farthermost from the roadway.

B. Underground Utilities. Utilities placed underground shall be placed within the right-of-way in accordance with the City's Standard Utility Location Cross-Section, or as otherwise approved by the Engineering Director on construction drawings for the project.

Figure 7.11.1

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:columbus-muscogee/zoning/7.11.1@2026-11-11-e1e3c0bd8e

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Columbus Zoning Ordinance, Section 7.11.1. Location of Utilities in Streets | Georgia Commons