Section 8.2.4. Record Drawings or As-built Surveys.
About this text
- As published by Municode, retrieved 2026-11-11
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
A. Record Drawings or As-built Surveys. Upon completion of the development activity as authorized by the development permit and prior to final development inspection of public and private improvements, the owner shall submit to the Department of Engineering for review and approval a complete set of record drawings showing "as-built" conditions prepared by a registered land surveyor.
Sanitary sewers and the public water system are under the jurisdiction of the Columbus Water Works, and plans shall be submitted to that department. These drawings shall show the location, vertical and horizontal alignment, and finished elevations of the improvements listed below:
1. Drainage system pipes and channels;
2. Bridges or culverts;
3. Stormwater detention facilities;
4. Sanitary sewer system (as required by the Columbus Water Works, if any);
5. Water system (as required by the Columbus Water Works, if any); and
6. Streets, including street centerlines showing angles of deflection and standard curve data of intersection, radii, length of tangents and arcs, and degree of curvature with basis of curve data.
B. Certification and Seal. The record drawings or as-built surveys shall be certified and sealed by a registered Land Surveyor, subject to the tolerances of accuracy indicated in the survey certification.