A. Scheduling a Building Inspection. Inspections shall be scheduled with the Director of Inspections and Code Enforcement at least 24 hours before the inspection is needed. Requests for inspection should include the street address, lot number, building permit number, and type of inspection. B. Required Inspections. The following types of inspections are required by the City. 1. Foundation. Verify minimum required building setbacks, footing, and trenches dug and reinforcing steel in place. 2. Plumbing Connections. Water supply line and sewer lateral in slab foundation. 3. Framing. Completion of all rough-ins and after insulation is installed. 4. Interior Walls. Interior walls may not be covered until the inspections listed below are completed. (A) Mechanical. Rough-ins complete with pressure test on gas line. (B) Electrical. Rough-ins with neutral, ground, and service cable wired. (C) Plumbing. Rough-ins complete and all fixtures installed. 5. Final Inspection. Building is complete and ready to occupy.