--- title: Cordele Zoning Ordinance, Section 1220. Solar energy facility or solar farm collection: local-codes id: local-code:cordele/zoning/1220 cite_as: Cordele, Ga., Zoning Ordinance § 1220 canonical_url: https://georgiacommons.org/code/local/cordele/zoning/1220 md_url: https://georgiacommons.org/code/local/cordele/zoning/1220.md text_url: https://georgiacommons.org/code/local/cordele/zoning/1220/text source_url: https://library.municode.com/ga/cordele/codes/code_of_ordinances date: 2026-11-11 status: active jurisdiction: city:cordele jurisdiction_name: Cordele place_fips: "1319616" corpus_version: local-codes-cordele-60ee2e0ac223 publisher: Georgia Commons, an independent project of Georgia Civic Data. Not the State of Georgia. Not legal advice. up: https://georgiacommons.org/code/local/cordele/zoning/~appendix-a/~article-xii.md previous: https://georgiacommons.org/code/local/cordele/zoning/1210.md next: https://georgiacommons.org/code/local/cordele/zoning/1230.md index: https://georgiacommons.org/code/local/cordele.md branch: zoning edition: As published by Municode, retrieved 2026-11-11 edition_date_kind: retrieved source_publisher: Municode version_id: local-code:cordele/zoning/1220@2026-11-11-b8e9a5e15c --- # Cordele Zoning Ordinance, Section 1220. Solar energy facility or solar farm > As published by Municode, retrieved 2026-11-11 > The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included. Part of: Appendix A - ZONING / Article XII - SOLAR PANEL USAGE In districts where permitted, a "solar energy facility" or "solar farm," shall be subject to the following regulations: (a) Location. Permitted Districts: LI, Light Industrial District HI, Highway Industrial District PW, Public Works District Prohibited Districts: R-12, Residential - Single Family, Low Density District R-7.5S, Residential - Single Family Medium Density District R-7.5, Residential - Single Family/Two Family, Medium Density District R-4, Residential - Multi-family District OI, Office & Industrial District NC, Neighborhood Commercial District CBD, Central Business District PEH, Park, Education, and Health District GC, General Commercial District HC, Highway Commercial District PD, Planned Development District (b) Mounting. 1. Solar panels or solar arrays shall be mounted onto a pole, rack or suitable foundation, in accordance with manufacturer specifications, in order to ensure the safe operation and stability of the system. The mounting structure (fixed or tracking capable) shall be comprised of materials approved by the manufacturer, which are able to fully support the system components, in accordance with applicable building permit requirements. Electrical components of the facility shall meet applicable electrical code requirements. 2. Multiple mounting structures shall be spaced apart at the distance recommended by the manufacturer to ensure safety and maximum efficiency. (c) Setbacks. A solar energy facility and its appurtenant components and structures shall be set back a minimum of 50 feet from all property lines and 100 feet from any residence. (d) Placement. 1. When located in agricultural zoning districts, the solar energy facility shall be located as much as possible to minimize impacts on prime agricultural soils. 2. If located in a floodplain or an area of known localized flooding, all panels, electrical wiring, automatic transfer switches, inverters, etc. shall be located above the base flood elevation. 3. Components of the facility shall not be located over a septic system, leach field area or identified reserve area unless approved by the Health Department. (e) Screening. The facility shall be fully screened from adjoining properties and adjacent roads using the natural topography or by installation of an evergreen buffer capable of reaching a height of 6 feet within three years of planting, with at least 75% opacity at the time of planting. (f) Height. 1. Freestanding solar panels or solar arrays shall not exceed 25 feet in height as measured from the grade at the base of the structure to the highest point. 2. Mounted solar panels or solar arrays shall not exceed eight feet above the apex of the structure on which it is mounted or the maximum height for buildings in the zoning district in which it is located. (g) Security. 1. Unless 24-hour security guards or video surveillance is provided at the installation, the solar energy facility shall be enclosed by a security fence no less than 6 feet nor greater than 8 feet in height. 2. Access gates and equipment cabinets must be locked when not in use. (h) Noise. Inverter noise shall not exceed 40dBA, measured at the property line. (i) Glare and Lighting. 1. The solar energy system components shall be designed with an antireflective coating or at least shall not produce glare that would constitute a nuisance to occupants of neighboring properties, aircraft, or persons traveling adjacent or nearby roads. 2. If lighting is required, it shall be activated by motion sensors, fully shielded and downcast type where the light does not spill onto any adjacent property or into the night sky. (j) Maintenance and Upkeep. Systems shall be maintained in accordance with manufacturer's specifications. The operator of the facility shall maintain the facility, including all buffer screening, in compliance with the approved plans and shall keep the facility free from weeds, dust, trash and debris. (k) Site Plan Review and Development Permit. A site plan reviewed and approved by the Planning Division shall be required prior to issuance of a development permit. In addition to requirements for site plans generally, the site plan submission shall include the following information: The proposed location and dimensions of all solar panels, inverters, existing and proposed structures, screening, fencing, property lines, parking, access driveways and turnout locations, ancillary equipment, transmission lines, vegetation, the location of any residences on site and within 100 feet of the perimeter of the facility, the location of any proposed solar access easements, and standard drawings of solar energy system components. (l) Additional Submission Requirements. In addition to requirements for information to be provided during the site plan review and development permitting process, the facility shall not be approved for operation until the following are submitted: 1. Copy of all lease agreements and solar access easements. 2. Where interconnection to an electric utility grid is proposed, the applicant shall submit evidence that the electrical utility provider has been informed of the customer's intent to install a connection with the local electric utility grid. A copy of the approval from the local utility must also be provided before operation of an interconnected facility will be authorized. 3. A decommissioning plan for the anticipated service life of the facility or in the event that the facility is abandoned or has reached its life expectancy. 4. The City may require other studies, reports, certifications, and/or approvals be submitted by the applicant to ensure compliance with this section. ## History (Ord. No. 2022-09, § 2, 11-2-22)