Sec. 109-364. Stormwater management—Report required.

About this text

  • As published by Municode, retrieved 2026-11-11
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

(a) A stormwater management report shall be submitted during the development review process for every project to which this article applies. A professional engineer currently registered in the state must prepare the report. The purpose of this report shall be to formulate a plan to manage the quantity and quality of stormwater runoff, so that stormwater runoff hazards are not created, existing runoff-related problems are not expounded, and that stormwater quality is not adversely

affected, either upstream or downstream from or within the boundaries of the property being developed.

(b) The stormwater management report shall identify the locations and quantities of stormwater runoff entering and exiting the site for both pre-developed and post-developed conditions. Analysis of the off-site properties may require anticipating future development in addition to addressing existing conditions. It shall contain drainage area delineation maps and other exhibits at a

satisfactory scale and sufficient in quantity and scope to define the boundaries of the site relative to any applicable watercourses, drainage divides, drainage structures and other pertinent features.

(c) The stormwater management report shall estimate the stormwater quality in terms of total suspended solids for both pre-developed and postdeveloped conditions.

(d) The analysis of downstream conditions in the report shall address each and every point or area along the project site's boundaries at which runoff will exit the property. The analysis shall focus on the portion of the drainageway immediately downstream from the project. In determining downstream effects from stormwater discharge control structures and the development, hydrologic-hydraulic engineering studies, using

the two-, ten-, and 25-year design storm, shall extend to the next downstream structure or shall extend downstream to a point where the proposed development represents less than ten percent of the total watershed. If the discharge calculations indicate that adjacent properties, between the exit of the proposed development and the ten percent downstream point, might be adversely impacted by the proposed development, then the engineer shall provide a summary of his recommendations.

(e) The site plan that is submitted in conjunction with the stormwater management report shall depict all streams, lakes, wetlands, and

other bodies of water. Additionally, the plan shall depict relevant the boundaries of the 100-year floodplain. The floodplain boundary information must be obtained using Federal Emergency Management Agency (FEMA) guidelines. One hundredyear base flood elevations (BFEs) for areas that are designated as approximate zone A on the city's

FEMA maps must be calculated using appropriate FEMA methodologies. Scaling off the FEMA maps to derive flood boundary information is

unacceptable and shall not be permitted.

(f) The following criteria shall be evaluated by the engineer preparing the stormwater management report:

(1) Existing land uses downstream.

(2) Anticipated future land uses downstream.

(3) Magnitude of increase in peak flows due to development.

(4) Presence of existing stormwater quality and/or quantity problems.

(5) Capacity of existing and anticipated drainage systems.

(6) Creation of concentrated flows where none had occurred previously.

(7) Existing flows generated off-site which pass through the project site.

(8) The nature of the receiving watercourse.

(9) All designs, calculations, and rationale must follow the principles set forth in the city stormwater manual.

History

The history line the source prints at the end of the section.

(Ord. of 3-16-2004(02), § III(10.8))

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:cumming/zoning/109-364@2026-11-11-03d1eef058

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Cumming Zoning Ordinance, Sec. 109-364. Stormwater management—Report required | Georgia Commons